Set off in construction contracts
Set off (sometimes called contra charging) is a legal process by which party A defends a claim brought by party B, by A setting off in extinction or diminution of B’s claim, claims which A alleges against B.
For example:
- A client might reclaim the cost of water damage to their property caused by a contractor fitting out the floor above the damaged area.
- A contractor might set off costs against a sub-contractor that caused damage to finished work adjacent to the working area of the sub-contractor.
- In the case of late completion a client might set off the appropriate amount of liquidated and ascertained damages in accordance with the contract.
Whilst set off is often accompanied by a counterclaim it is to be distinguished in that set off cannot, unlike a counterclaim, give rise to a positive balance of claim.
Set off rights can either be contractual, equitable or in the case of insolvency, statutory.
Contractual set off will depend on the wording of the agreement between the parties. It is possible for contractual set off rights to extend to a wide range of different contracts, but the wording must be clear. Equitable set off arises by operation of law if there is sufficient proximity and connection between the parties (e.g. the same parties, site and project). A recent statement of the law of equitable set off is given in the Court of Appeal judgement in Geldof Metaalconstructie NV v Simon Carves Ltd [2010].
If a contracting party becomes insolvent, the Insolvency Act 1986 Section 323 (bankruptcy) and the Insolvency Rules Rule 4.90 (liquidation) provide for a statutory set off known as ‘mutual credits and mutual debits’.
This statutory set off requires account to be taken between the insolvent party and the proving creditor of mutual debts, mutual credits and mutual dealings arising before the insolvency which are then set off leaving only the balance, if any, provable in the insolvency. This is, of course, only fair as otherwise the creditor would be 100% liable on debts due to the insolvent and only receive the relevant distribution (often nothing) on debts owed by the insolvent.
In construction contracts, rights of set off and withholding payments are regulated by the Housing Grants, Construction and Regeneration Act 1996 Part II Section 111, amended, with effect from October 2011, by the Local Democracy, Economic Development and Construction Act 2009 Part 8 Section 144. These Acts regulate the contents and prescribed periods for 'pay less' notices which must be served if a party wishes to deduct sums from amounts otherwise due under the contract.
Adjudication procedures constrain the effect of set off to preserve the public policy of adjudication that it should be a relatively speedy interim solution. In M J Gleeson Group Plc v Devonshire Green Holding Ltd [2004], the court held that a respondent could not set off claims arising after the commencement of the adjudication to avoid payment of a sum awarded by the adjudicator.
See also Section 111 (4) Housing Grants, Construction and Regeneration Act.
[edit] Related articles on Designing Buildings Wiki
- Abatement.
- Adjudication.
- Alternative dispute resolution.
- Contract.
- Contract conditions.
- Counterclaim.
- Housing Grants, Construction and Regeneration Act.
- Liquidated and ascertained damages.
- Mediation.
- Scheme for Construction Contracts.
[edit] External references
Featured articles and news
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.
























Comments