Abatement in construction
Abatement is a defence against a claim for payment where it is argued that the amount claimed is incorrect because of defects in the work. If the defect is proved, then the valuation of the amount due may be reduced by the reduction in value of the works resulting from the defect. Abatement only applies to payment for labour and materials, not to professional services or to losses resulting from delay or disruption. Abatement exists as a common law right.
Abatement is often confused with set off. Set off (or contra charging) requires that a breach of contract can be demonstrated. It can permit the withholding or extinguishing of an agreed payment. Set off can be used to recover the costs of rectifying defects and any delay. Whilst set off is often accompanied by a counterclaim it is to be distinguished in that set off cannot, unlike a counterclaim, give rise to a positive balance of claim. Set off rights can either be contractual, equitable or in the case of insolvency, statutory.
Before the 2011 amendments to the Housing Grants Construction and Regeneration Act, set off and counterclaim were only permitted if a withholding notice was issued, whilst abatement did not require a withholding notice as the value of the works had been reduced and there was only an obligation to pay the amount properly due.
Since 2011 however, set off, counterclaim and abatement all require that a pay less notice is issued.
[edit] Related articles on Designing Buildings
Featured articles and news
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.
UKCW London to tackle sector’s most pressing issues
AI and skills development, ecology and the environment, policy and planning and more.
Managing building safety risks
Across an existing residential portfolio; a client's perspective.
ECA support for Gate Safe’s Safe School Gates Campaign.
Core construction skills explained
Preparing for a career in construction.
Retrofitting for resilience with the Leicester Resilience Hub
Community-serving facilities, enhanced as support and essential services for climate-related disruptions.
Some of the articles relating to water, here to browse. Any missing?
Recognisable Gothic characters, designed to dramatically spout water away from buildings.
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.

























Comments
Abatement is a defence against a claim for payment where it is argued that the amount claimed is incorrect because of defects in the work. If the defect is proved, then the valuation of the amount due may be reduced by the reduction in value of the works resulting from the defect.