Named specialist work in construction
In February 2013, a change was introduced to the JCT Standard Building Contract 2011 enabling an employer to identify specialists to be used as domestic sub-contractors (that is specialists subcontracted by the main contractor) for identified parts of the works by appropriate entry in the contract particulars.
This provides the opportunity for the employer to select a sub-contractor with particular expertise, whilst leaving responsibility for their performance with the main contractor.
This is similar to provisions for named subcontractors in some other forms of contract, and its inclusion is seen to be a result of the omission of provisions for nominated subcontractors from the JCT Standard Building Contract since 2005.
If the naming of specialists is required, a series of standard clauses and amendments must be incorporated into the contract. There are two ways in which the specialist provisions can work:
- Pre-named specialist work: The specialist may be named in the contract together with the work to be carried out.
- Post-named specialist work: A provisional sum may be inserted in the bill of quantities, allowing the contract administrator to issue an instruction to name the specialist and identify the works required.
Upon receiving an instruction from the contract administrator in relation to a post-named specialist or a replacement specialist, the contractor is able to raise reasonable objection within seven days. The contract administrator then has a further seven days to either:
- Name an alternative specialist.
- Instruct the contractor to undertake the work itself or through its own sub-contractor.
- Omit the work altogether.
This may entitle to contractor to an extension of time and /or loss and expense.
The contractor should enter into a contract with the specialist as soon as ‘reasonably practicable’ using a JCT Standard Building Sub-Contract.
The contract administrator must be notified if a contract cannot be entered by the contractor as required. On receipt of this notification the contract administrator must provide instruction to the contractor to either:
- Remove or solve whatever is preventing the contract.
- Select an alternative specialist.
- Undertake the work itself.
- Omit the work altogether.
If the contractor wishes to terminate the specialist’s employment, they must notify the contract administrator and, if required, the employer. The contractor can only give notice of termination or of repudiation after 14 days, unless the specialist has become insolvent.
If the contractor terminates the specialist’s employment, the contract administrator must issue instructions to the contractor to either:
- Name an alternative specialist.
- Undertake the work itself or through its sub-contractor.
- Omit the work altogether.
If the named specialist becomes insolvent the contractor may be entitled to an extension of time and /or loss and expense.
[edit] Related articles on Designing Buildings Wiki:
- Articles of agreement.
- Attestation in construction.
- Construction contracts.
- Contract conditions.
- Contract documents.
- Extension of time.
- Intermediate Building Contract.
- Joint Contracts Tribunal.
- Loss and expense.
- Named subcontractor.
- Nominated subcontractor.
- Nominated subcontractor v named subcontractor.
- Operative.
- Reasonable objection to a named specialist.
- Repudiation.
- Selected subcontractor.
- Specialist subcontractor.
- Sub-contract.
- Subcontractor.
- Supplier.
[edit] External references
- ‘The JCT Standard Building Contract 2011’, CHAPPELL, D., John Wiley and Sons (2015)
Featured articles and news
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.