Named specialist work in construction
In February 2013, a change was introduced to the JCT Standard Building Contract 2011 enabling an employer to identify specialists to be used as domestic sub-contractors (that is specialists subcontracted by the main contractor) for identified parts of the works by appropriate entry in the contract particulars.
This provides the opportunity for the employer to select a sub-contractor with particular expertise, whilst leaving responsibility for their performance with the main contractor.
This is similar to provisions for named subcontractors in some other forms of contract, and its inclusion is seen to be a result of the omission of provisions for nominated subcontractors from the JCT Standard Building Contract since 2005.
If the naming of specialists is required, a series of standard clauses and amendments must be incorporated into the contract. There are two ways in which the specialist provisions can work:
- Pre-named specialist work: The specialist may be named in the contract together with the work to be carried out.
- Post-named specialist work: A provisional sum may be inserted in the bill of quantities, allowing the contract administrator to issue an instruction to name the specialist and identify the works required.
Upon receiving an instruction from the contract administrator in relation to a post-named specialist or a replacement specialist, the contractor is able to raise reasonable objection within seven days. The contract administrator then has a further seven days to either:
- Name an alternative specialist.
- Instruct the contractor to undertake the work itself or through its own sub-contractor.
- Omit the work altogether.
This may entitle to contractor to an extension of time and /or loss and expense.
The contractor should enter into a contract with the specialist as soon as ‘reasonably practicable’ using a JCT Standard Building Sub-Contract.
The contract administrator must be notified if a contract cannot be entered by the contractor as required. On receipt of this notification the contract administrator must provide instruction to the contractor to either:
- Remove or solve whatever is preventing the contract.
- Select an alternative specialist.
- Undertake the work itself.
- Omit the work altogether.
If the contractor wishes to terminate the specialist’s employment, they must notify the contract administrator and, if required, the employer. The contractor can only give notice of termination or of repudiation after 14 days, unless the specialist has become insolvent.
If the contractor terminates the specialist’s employment, the contract administrator must issue instructions to the contractor to either:
- Name an alternative specialist.
- Undertake the work itself or through its sub-contractor.
- Omit the work altogether.
If the named specialist becomes insolvent the contractor may be entitled to an extension of time and /or loss and expense.
[edit] Related articles on Designing Buildings Wiki:
- Articles of agreement.
- Attestation in construction.
- Construction contracts.
- Contract conditions.
- Contract documents.
- Extension of time.
- Intermediate Building Contract.
- Joint Contracts Tribunal.
- Loss and expense.
- Named subcontractor.
- Nominated subcontractor.
- Nominated subcontractor v named subcontractor.
- Operative.
- Reasonable objection to a named specialist.
- Repudiation.
- Selected subcontractor.
- Specialist subcontractor.
- Sub-contract.
- Subcontractor.
- Supplier.
[edit] External references
- ‘The JCT Standard Building Contract 2011’, CHAPPELL, D., John Wiley and Sons (2015)
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.





















