Retention bond
Retention is a percentage (often 5%) of the amount certified as due to the contractor on an interim certificate that is retained by the client. The purpose of retention is to ensure the contractor properly completes the works required under the contract.
Half of the amount retained is released on certification of practical completion and the remainder is released upon certification of making good defects. Retention due to subcontractors may in turn be held by the main contractor and so on down through the contractual chain.
The recovery of retention is often a difficult area for parties in the contractual chain and cash flow problems frequently arise resulting from non-payment. In theory, this should be prevented by the Housing Grants Construction and Regeneration Act which disallows ‘pay when paid’ clauses, however, retention is commonly not released on time or in accordance with the contract. For subcontractors in particular, the release of retention may rely on circumstances outside of their contract or their control, for example, defects being remedied under the main contract by other parties.
Retention bonds are way of avoiding problems associated with retention recovery. Amounts that would otherwise have been held as retention are instead paid, with a bond being provided to secure the amount. Similar to retention, the bond’s value will usually reduce after the certification of practical completion.
Only if practical completion is not achieved by the subcontractor or if they prevent a certificate of making good defects from being issued will the retention bond take effect. The contractor is then able to ‘call’ on the retention bond.
A subcontractor is usually allowed a fixed period of time to rectify any defects, and this is stipulated by the retention bond. Should they fail to rectify the defect, the retention bond can be called on by the contractor and the surety must cover the remedial costs, before then pursuing the subcontractor.
Whilst subcontractors must pay the surety’s premiums, the benefit to them is that they do not have to chase retention monies post-completion, and no retention monies will be withheld. This cash flow security is often seen as worth the cost of the premium. Similarly, retention bonds are advantageous to contractors in improving the cash flow and financial stability of the subcontractor, making them less likely to default on the works.
Retention bonds include a fixed expiry date, making it clear when the subcontractor is released from its obligations.
Retention bonds may also be used as an alternative to retention between the employer and the main contractor.
[edit] Related articles on Designing Buildings Wiki
- Advance payment bond.
- Bonds and guarantees (Aviva Insurance Limited v Hackney Empire Limited 2012).
- Bonds in construction contracts.
- Campaign for cash retentions reform.
- Certificate of making good defects.
- Construction (Retention Deposit Schemes) Bill 2017-19.
- Defects.
- Defects liability period.
- Final account.
- Holdback.
- Parent company guarantee.
- Performance bond.
- Practical completion.
- Retainage.
- Retention.
- Retention held in trust fund.
- Sub-contractor.
- The problems with retention.
- Zero-coupon bond.
[edit] External references
Featured articles and news
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach £7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
How to write an inspection and test plan
ITPs for quality control and assurance particular elements.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Winners of the 2024 ASBP Awards
Project, Product and Initiative according to the 6 pillars.