Contractual chain
It is common practice on construction projects to have more than one set of parallel contractual arrangements in place. On the one hand there is the main contract between the employer (client) and the main contractor; on the other hand, there is the sub-contract between the main contractor and the sub-contractor or sub-contractors. Each of these contractual arrangements is regarded as a link in the overall contractual chain.
One of the features of the contractual chain is the privity of contract. This means that the rights and obligations contained in the contract apply only to those who are a party to it. So, the main contract between the client and main contractor does not involve the sub-contractor who is therefore not liable contractually to the client for any actual breach of contract. The subcontractor therefore cannot claim against the client for say, poor working conditions or for retention monies held by the main contractor which have yet to be received. The sub-contractor must claim against the main contractor.
Likewise, the sub-contract between the main contractor and the sub-contractor does not involve the client. If the client wishes to claim against the sub-contractor, whether for the latter committing breach of contract or for defective work, the claim must be redressed by the main contractor. In such cases, the sub-contractor is liable to the main contractor.
There is usually no privity of contract between the client and the sub-contractor (whether nominated or domestic). So, for whatever breach of contract, fault or misdemeanour, the sub-contractor is not usually liable to the client. Which means the client cannot claim against the sub-contractor but must recover any due costs from the main contractor (with whom they have privity of contract). The main contractor in turn recovers the costs from the sub-contractor. This amounts to a chain of liability, where recovering costs requires either going up or down the contractual chain.
Problems can arise where the chain involves a weak link. For example, if the terms of the main contract and the sub-contract are not comparable, are incompatible or are just different, relying on the chain of liability could be problematic. There may be a break in the chain which would see the sub-contractor unable to recover any payments or compensation which are rightly due.
On large or complex projects, responsibility and performance generally cascades down the supply chain to a plethora of suppliers, some of whom may be entirely unknown to management at the top of the chain.
For more information see: Supplier and Supply chain.
NB Collateral warranties are agreements which are associated with another 'primary' contract. They provide for a duty of care to be extended by one of the contracting parties to a third party who is not party to the original contract. A typical example would be where an architect of a development owes a duty of care to an occupier of the development in so far as any subsequent defects which may arise are concerned. Privity of contract rules would prevent any liability arising between the architect and occupier without the existence of a collateral warranty.
For more information see: Collateral warranty.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Specifying XPS in masonry cavity walls below DPC level
Moisture requirements, DPCs and third party certification.
Types of rigid foam insulation
A brief description and some of the main construction types.
Metal composite material panel systems MCM and MCP
Sandwich finishes, forms, details, core and their impacts.
Cumbria's vernacular architecture
A history of building impeded by unsettled times.
CIOB and MMC Ireland announce strategic partnership
For better working conditions, and a more productive construction sector.
More than just glass.
Grenfell Phase 2 final report for construction, at a glance
Twenty-three key issues raised and their recommendations.
Industry responds to the final Grenfell inquiry phase 2 report
Construction body responses to the long-awaited 7 volumes.
Chief construction advisers in brief
From July 2008 to November 2015.
The Grenfell phase 2 final report key summary points
And recommendations for the construction industry.
Approved Document B: Fire Safety upcoming updates
Including sprinklers in care homes, National classes and Fire resistance.
CIOB Podcast: 21st Century Construction
Catch up on the many previous episodes.
Tools and processes supporting a robust golden thread
BSRIA Handover Information and O&M Manuals guidance.
Industry survey highlights persistent skills gap
Building engineering business survey by ECA in partnership with BESA, SELECT and SNIPEF.
IHBC Conservation Professional Practice Principles
Spotlighted in HEF Historic Environment Overview.
CIAT collaborates with CIOB, CIfA, Icon to launch The Arc
Helping clients find specialist historic environment professionals.
Government building safety remediation data releases
Show some progress, but a 50% gap not yet started.
Testing For A Safer Future; an initial industry response
A response to the Independent Review of the Construction Product Testing Regime.
Requirements for UK buildings in certain circumstances.