Bonds in construction contracts
Contents |
[edit] Introduction
Bonds are a means of protection against the non-performance of the contractor. They are an undertaking by a bondsman or surety to make a payment to the client in the event of non-performance of the contractor. The cost of the bond is usually borne by the contractor, although this is likely to be reflected in the contractor's tender price.
Bonds can be 'on demand' or 'conditional', with conditional bonds requiring that the client provides evidence that the contractor has not performed their obligations under the contract and that they have suffered a loss as a consequence.
See also Bonds v guarantees.
[edit] Performance bond
A performance bond is commonly used as a means of insuring a client against the risk of a contractor failing to fulfil contractual obligations to the client, although they can also be required from other parties.
Performance bonds are typically set at 10% of the contract value. This compensation can enable the client to overcome difficulties that have been caused by non-performance of the contractor, such as, finding a new contractor to complete the works.
For more information, see Performance bond.
[edit] Advance payment bond
If the client agrees to make an advance payment to the contractor, (for example where the contractor incurs significant start-up and procurement costs before construction begins), a bond may be required to secure the payment against default by the contractor. This will normally be an on-demand bond.
For more information, see Advance payment bond.
[edit] Off-site materials bond
It can sometimes be appropriate for the client to pay for items even though they remain ‘off-site’. For example, where a contractor has made a large payment for plant or materials that have yet to be delivered to site, or if the client wishes to ‘reserve’ key items in order to protect the programme.
This is similar to the situation where an advanced payment is made in that a bond secures the payment against default by the contractor and is likely to be an on-demand bond. The bond might be up to the value of the off-site items, with the value of the bond reducing as deliveries to site are made.
[edit] Bid bond (or tender bond)
Bid bonds are rare in the UK, but can be a requirement of an international tender process. They are usually on-demand bonds submitted with a tender to secure the tenderer's commitment to commence the contract. The bond is partially or fully forfeited if the winning tenderer fails to execute the contract or meet other specified conditions.
Bid bonds can be open to abuse by the client and may prevent smaller companies from tendering.
For more information, see Bid bond.
[edit] Retention bond
Retention is a percentage (often 5%) of the amount certified as due to the contractor on an interim certificate that is retained by the client. The purpose of retention is to ensure the contractor properly completes the activities required of them under the contract. Half of the amount retained is released on certification of practical completion and the remainder is released upon certification of making good defects.
An alternative to retention is a retention bond, where the client agrees to pay the amounts which would otherwise have been held as retention, but instead a bond is provided to secure the amount that would have been retained. As with retention, the value of the bond will usually reduce after practical completion has been certified.
[edit] Defects liability bond (or defects liability demand guarantee)
The defects liability period (now called the 'rectification period' in Joint Contracts Tribunal (JCT) contracts) begins upon certification of practical completion and typically lasts six to twelve months. During this time, it is the contractor's responsibility to rectify any defects that become apparent in the works.
A defects liability bond can be used to ensure that the contractor continues to provide services, rectifying defects that become apparent after practical completion has been certified. This is generally an on-demand bond that may be required on projects where there are no remaining payments to be made, or other security such as retention, after practical completion.
[edit] Adjudication bond
Adjudication is a contractual or statutory procedure for swift dispute resolution. Adjudication is provided by a third-party adjudicator selected by the parties to the dispute.
Adjudication bonds are conditional bonds that have emerged on PFI/PPP projects and are payable on an adjudicator's decision. Adjudication bonds are most suitable when the adjudicator’s decision is final and binding. If this is not the case (i.e. the adjudicator’s decision is an interim one), complex procedures are necessary to balance payments if subsequent dispute resolution procedures reach different decisions.
[edit] Related articles on Designing Buildings
- Advance payment bond.
- Bid bond.
- Bonds and guarantees.
- Bondsman.
- Campaign for cash retentions reform.
- Comfort letter.
- Contractor bonding.
- Escrow.
- Parent company guarantee.
- Performance bond.
- Professional consultant's certificate.
- Retention.
- Retention bond.
- Surety.
- Warranty.
- Wuhan Guoyu Logistics Group Co Ltd & Anr v Emporiki Bank of Greece SA (2013).
- Zero-coupon bond.
Featured articles and news
Ebenezer Howard: inventor of the garden city. Book review.
Grenfell Tower fire – eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.
BSRIA Sentinel Clerk of Works Training Case Study
Strengthening expertise to enhance service delivery with integrated cutting-edge industry knowledge.
Impact report from the Supply Chain Sustainability School
Free sustainability skills, training and support delivered to thousands of UK companies to help cut carbon.
The Building Safety Forum at the Installershow 2025
With speakers confirmed for 24 June as part of Building Safety Week.
The UK’s largest air pollution campaign.
Future Homes Standard, now includes solar, but what else?
Will the new standard, due to in the Autumn, go far enough in terms of performance ?
BSRIA Briefing: Cleaner Air, Better tomorrow
A look back at issues relating to inside and outside air quality, discussed during the BSRIA briefing in 2023.
Restoring Abbotsford's hothouse
Bringing the writer Walter Scott's garden to life.
Reflections on the spending review with CIAT.
Retired firefighter cycles world to raise Grenfell funds
Leaving on 14 June 2025 Stephen will raise money for youth and schools through the Grenfell Foundation.
Key points for construction at a glance with industry reactions.
Comments
If you need Performance Bonds, Nationwide Sureties have a number of options that can assist you at tender or after winning your Contract, to help you deliver.