Non-performance in the construction industry
Non-performance is a general term that describes a party which fails to perform; in fact, the term can cover all forms of failure in performance. A student who fails end-of-year exams may be regarded by the school as a non-performer. In this respect, non-performance is not contractually linked – the student never promised to do well and there was no contact entered into, written or otherwise.
In simple terms, a contract is a legally-binding promise. From a legal perspective, the basis of every contract is that all parties must fulfil all of the contract's terms. Non-performance occurs when one party to the contract does not fulfil the contract terms – failing to live up to their contractual obligations. Such a failure is not necessarily a breach of contract although it could lead to a breach of contract.
A breach of contract in English Law is non-performance that is not excused because it is the non-performance of a contractual obligation, i.e. a promise was made and was not kept. A breach of contract entitles the innocent party to receive damages from the guilty party. It may also allow the innocent party the right to terminate the contract.
An example of non-performance is a contractor who fails to provide sufficient labour, materials or equipment to a project, leading to a delay to the completion date.
Bonds can provide a degree of protection for the client. Bonds are an undertaking by a bondsman or surety to make a payment in the event of non-performance. Bonds can be 'on demand' or 'conditional', with conditional bonds requiring that the client provides evidence of the contractor's non-performance, and that as a consequence the client has suffered a loss.
[edit] Refusal to perform or declaration of non-performance
A declaration of non-performance is another form of non-performance. One party declares they are abandoning any further performance under the contract or refuses to fulfil an essential aspect of the contract. In this case, the innocent party can discharge themselves from any further performance obligations.
[edit] Related articles on Designing Buildings Wiki
- Bonds in construction contracts.
- Construction contract conditions
- Contractual obligation.
- Contractual right.
- Delay analysis.
- JCT
- JCT Construction management contract
- Performance bond
- Procurement team
- Standard form of contract
- Tender documentation for construction projects
- Traditional contract for construction
- Traditional contract: tender
- Typical tender process for construction projects
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.