Traditional contract for construction
The 'traditional' procurement route, sometimes referred to as 'design bid build', 'bid build' or 'employer designed' remains the most commonly used method of procuring building works.
The client first appoints consultants to design the project in detail and then prepare tender documentation, including drawings, work schedules and bills of quantities. Contractors are then invited to submit tenders for the construction of the project, usually on a single-stage, competitive basis. This may be referred to as a 'traditional contract'. The contractor is not responsible for the design, other than temporary works, although some traditional contracts do provide for the contractor to design specific parts of the works.
Typically, the client retains the design consultants during the construction phase to prepare any additional design information that may be required, to review any designs that might be prepared by the contractor, and to inspect the works. Normally, one consultant (often, but not necessarily, the architect) will be appointed to administer the contract.
Traditional construction contracts are most commonly lump-sum contracts, however, measurement contracts and cost reimbursement contracts can also be used for ‘traditional’ projects where design and construction are separate, sequential activities.
This form of procurement is suitable for both experienced and inexperienced clients. Fully developing the design before tender gives the client certainty about design quality and cost, but it can be slower than other forms of contracting, and as the contractor is appointed only once the design is complete, they are not able to help improve the buildability and packaging of proposals as they develop.
It is considered to be a low risk method of contracting for the client, as the contractor takes the financial risk for construction. However, if design information is incomplete at tender, or if significant variations are required after the contractor has been appointed, the cost to the client can be significant. Because of this, and because of the separation of design and construction, traditional procurement can be seen as adversarial.
See also: Traditional contract - pros and cons.
The most common forms of traditional contract remain the JCT (Joint Contracts Tribunal) Standard Building Contract, Intermediate Building Contract and Minor Works Building Contract.
When might it be appropriate?
- If the employer has had the design prepared
- If the design is substantially completed at time of contractor selection
- The client wishes to retain control over the design and specification
- Cost certainty at start on site is important
- The shortest overall programme is not the client’s main priority.
What are the advantages of traditional procurement?
- Competitive fairness and transparent process.
- Design led – can ensure quality
- Price certainty before commencement
- Well known procedures
- Changes are reasonably easy to arrange and value
What are the disadvantages?
- Overall project duration may be longer than other procurement routes – sequential process
- No input into design and planning by the contractor
- Strategy based on price competition – could lead to adversarial relations
- Dual point of responsibility – design team for design and contractor for construction
- If the design is not complete at the time of tender, cost and time certainty are reduced.
For a detailed description of the sequence of activities necessary on a traditional contract see the work plan: Traditional contract: outline work plan.
[edit] Related articles on Designing Buildings
- Atkins v Secretary of State for Transport.
- Appointing consultants.
- Bill of quantities.
- Client.
- Construction contract.
- Contract conditions.
- Contractor.
- Design quality.
- Job order contracting.
- Notifications during construction works
- Procurement route.
- Temporary works.
- Tender.
- Tender documentation.
- Traditional contract: outline work plan.
- Traditional contract - pros and cons.
- Two-stage tender.
- Variations.
[edit] External references
Featured articles and news
More than just glass.
Grenfell Phase 2 final report for construction, at a glance
Twenty-three key issues raised and their recommendations.
Industry responds to the final Grenfell inquiry phase 2 report
Construction body responses to the long-awaited 7 volumes.
Chief construction advisers in brief
From July 2008 to November 2015.
The Grenfell phase 2 final report key summary points
And recommendations for the construction industry.
Approved Document B: Fire Safety upcoming updates
Including sprinklers in care homes, National classes and Fire resistance.
CIOB Podcast: 21st Century Construction
Catch up on the many previous episodes.
Tools and processes supporting a robust golden thread
BSRIA Handover Information and O&M Manuals guidance.
Industry survey highlights persistent skills gap
Building engineering business survey by ECA in partnership with BESA, SELECT and SNIPEF.
IHBC Conservation Professional Practice Principles
Spotlighted in HEF Historic Environment Overview.
CIAT collaborates with CIOB, CIfA, Icon to launch The Arc
Helping clients find specialist historic environment professionals.
Government building safety remediation data releases
Show some progress, but a 50% gap not yet started.
Testing For A Safer Future; an initial industry response
A response to the Independent Review of the Construction Product Testing Regime.
Requirements for UK buildings in certain circumstances.
CLC guidance for dutyholders and accountable persons.
Types of contractor in the construction industry
A long list, but are any missing ?
The Housing (Cladding Remediation) (Scotland) Bill 2023
Unanimously approved to legislation on May 14, 2024.
Where it's AT Building Safety podcasts from CIAT
Unravelling the Golden Thread and CIAT’s Principal Designer Register for non-HRBs and HRBs.
Comments