Two-stage tender
Contents |
[edit] What is two-stage tendering?
Two stage-tendering is a way of procuring goods or services that involves two-stages of appointment. Traditionally, tendering involves just one stage, in which a tenderer is selected and appointed to carry out all of the works required. In Two-stage tendering, the tenderer is initially appointed only to carry out some of the works required. They are generally then appointed to carry out the rest of the works in a second stage.
[edit] When is two-stage tendering used?
Two stage tendering is often used to allow the early appointment of a contractor (or other supplier), prior to the completion of all the tender information that they would require to be able to offer the client a fixed price - ie the design is still being developed. In the first stage therefore, a limited appointment is agreed allowing the contractor to begin work and in the second stage a fixed price is negotiated for the contract.
It can be used to appoint the main contractor early, but more commonly it is used as a mechanism for early appointment of a specialist contractor such as a cladding contractor in order to access their specialist advice which may be necessary to properly complete the design.
It may also be used on a design and build project where the employer's requirements are not sufficiently well developed for the contractor to be able to calculate a realistic price. In this case, the contractor will tender a fee for designing the building (or completing the design) along with a schedule of rates that can be used to establish the construction price for the second stage tender.
[edit] How are first-stage appointments made?
The first-stage appointment might be made on the basis of a bespoke agreement, a consultancy agreement or a pre-construction services agreement (PCSA), with an appendix setting out all tender items to be applied to the second stage contract, and a clause that makes it clear there is no obligation to proceed to the second stage, and in such circumstances the first stage fee would be full and final settlement of the contractor's costs.
The basis of the appointment for the first stage may include:
- A pre-construction and construction programme.
- Method statements.
- Detailed preliminaries including staff costs.
- Agreed overheads and profit.
- A schedule of rates to be applied to the second-stage tender.
- Agreed fees for design and other pre-construction services.
- CVs for proposed site and head office staff.
- Tendering of any packages that can be broken out and defined.
- Agreed contract conditions to be applied to the second-stage construction contract.
It is important that this appointment is based on as much information as possible and that requirements are well defined, as subsequent changes could prove expensive.
The pre-construction services carried out by the contractor in the first phase might include:
- Helping the consultant team develop the design, or the contractor undertaking all design development themselves.
- Helping the consultant team develop the method of construction, or the contractor developing the method of construction themselves.
- Obtaining prices for work packages from sub-contractors or suppliers on an open book basis.
It is in the client's interests to try to include some packages in the first phase, and to ensure that they have some means of securing an alternative bid if negotiations with the preferred contractor fail, albeit this is likely to result in delays and difficulties regarding design liability. However, the client may find the competition lose interest once they find out that another contractor been awarded the first stage tender.
[edit] How is the second stage appointment made?
Ideally the second-stage negotiation is simply a mathematical exercise using the pricing criteria agreed in the first stage agreement. In reality however, there will be some items not previously considered, around which negotiations will ensue. In the case of sub-contractors, the second stage construction contract is negotiated by the main contractor subject to the approval of the design team.
NB: On a management contract, a single agreement is likely to cover both pre-construction and construction services, with a notice to proceed between the two, before which works contracts cannot be let.
[edit] What are the benefits of two-stage tendering?
Two-stage tendering can allow a project to progress before the design is complete. Early involvement of the contractor (or other supplier) should also improve the buildability and cost-certainty of the design as well as creating a better integrated project team and reducing the likelihood of disputes.
Two-stage tendering enables the client to transfer design risk to the contractor, however the client inevitably loses leverage as the contractor becomes embedded in the team and competition is less of a threat. However, whilst tender prices for two-stage contracts may initially be higher than single-stage tenders, which are subject to full competition, the final account tends to include fewer variations and fewer claims. A longer period of familiarity with the project creates better relationships as well as a reduction in learning curves and programme performance.
[edit] Related articles on Designing Buildings
- Appointing consultants.
- Competitive tender.
- Construction contract.
- Design and build.
- Early contractor involvement.
- Integrated project team.
- Open book accounting.
- Optimised contractor involvement.
- Pre-construction services agreement.
- Preliminaries.
- Procurement route.
- Single-stage tender.
- Specialist contractor.
- Sub contractor.
- Tender.
- Tender processes.
- Two stage open book.
[edit] External references
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
Hi folks,
the definitions of the first stage and the second stage are not the same in this article and the rics article referenced at the bottom.
Can we get some clarity on which is the correct interpretation?
There are different forms of two-stage tendering depending on the nature of the project and what the client is trying to achieve.