Early appointment / involvement
Contents |
[edit] Introduction
Early appointment typically refers to the involvement at the earliest possible stage in the design process of certain stakeholders to a construction project, with the aim of fostering partnering and improved team working. This will help ensure a project environment that manages risk, encourages innovation, improves collaboration, is less adversarial, and minimises unforeseen costs and delays – all of which can help deliver value for money.
[edit] Contractor
Early contractor involvement (ECI) allows contractors to participate in both the design development and construction planning stages. This can be essential for some projects, especially very large or complex projects and particularly those that rely on building information modelling (BIM), or where speed it important.
ECI clauses are now part of NEC contracts which are published by the Institution of Civil Engineers (ICE). A single NEC3 Engineering and Construction Contract (ECC) can be used for both stages where contractors are participating. ICE has suggested that early contractor involvement “...supports improved team working, innovation and planning to deliver value for money”.
ECI allows the contractor to input contractual, construction and design experience and ideas at an early stage in consultation with the client, architect, engineer and other consultants. In so doing, the contractor can influence the design in a beneficial way, advise on constructability, cost estimating, in-use performance, construction sequencing, materials and lead times, site considerations and a host of other matters that the client and other consultants may not have as much experience of. This means the contractor becomes familiar with the project over a longer period of time and can help avoid costly mistakes and delays.
The client (or employer) can appoint the contractor to help its consultants with the project design or to design specific elements. This is normally followed by the contractor being asked to deliver the works. Alternatively, the client can appoint the contractor to deliver the design helped by the client’s consultants.
For more information see: Early contractor involvement.
[edit] Key sub-contractors and suppliers
Early involvement of key sub-contractors and suppliers in the design process can also have benefits for a project such as establishing market pricing for the work involved, contributing to the design process, developing long lead time items and so on. This can also help the client, sub-contractors, suppliers and main contractor mitigate risk.
[edit] Other stakeholders
Community ‘buy-in’ (local residents, businesses, politicians and community groups and so on) at an early stage in a construction project can result in benefits for a project. Informed stakeholders that are part of the dialogue can enhance a project, avoiding potentially disruptive community relations and bad publicity. An involved community will more likely lend its support to a project.
Educating the community about a project’s goals is based primarily on providing information and inviting dialogue at workshops, meetings and other events which:
- Allow the community to generate ideas for project planning and implementation;
- Helps establish project sustainability and discovers what the community thinks and needs;
- Improves community relations and
- Gives the community a sense of empowerment that fosters acceptance.
For more information see: Stakeholder management.
[edit] Related articles on Designing Buildings Wiki
- Collaborative practices.
- Construction contract.
- Contract conditions.
- Contractor's design portion.
- Defined cost.
- Delay damages.
- Early contractor involvement.
- Institution of Civil Engineers.
- JCT.
- Latham Report
- Management contract.
- NEC contract change management systems.
- NEC3.
- Optimised contractor involvement.
- Procurement route.
Featured articles and news
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
The ECA Industry Awards 2024 now open !
Recognising the best in the electrotechnical industry.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding..