Construction contract conditions
Contract conditions set out the principal legal relationship between the parties to a construction project, determining the allocation of risk and consequently, price.
English law, unlike the codified legal systems in Europe which recognise a duty of good faith, is not concerned with fairness but with certainty (unless it is a consumer contract protected by statute such as the Consumer Protection Act 1987 or the Unfair Contract Terms Act 1977).
The construction sector has a wide range of standard forms of contract which are intended to balance the risk of the parties but more importantly, through extensive and repeated use, give rise to a certainty of meaning. Well-known standard form contracts include the Joint Contracts Tribunal (JCT), the New Engineering Contract (NEC) and for international projects Fédération Internationale des Ingénieurs-Conseil (FIDIC).
See the article on Contracts for more information.
Standard form contracts also provide for different procurement routes, such as:
- Construction management.
- Design and build.
- Design build finance and operate (PPP / PFI / DBO / BOOT).
- Emerging cost contracts.
- Engineering Procurement and Construction Contract (EPC) / Turnkey contract
- Engineering Procurement and Construction Management contract (EPCM)
- Furniture, Fixtures and Equipment contract (FF&E).
- Framework agreements.
- Management contract.
- Measured term contracts
- Measurement contract ('re-measurement' or ‘measure and value’ contract)
- Partnering.
- Prime cost contract / cost plus contract / cost reimbursable contract
- Prime contracting / prime-type contracting
- Traditional contract.
See the article on Procurement routes for more information.
Typical conditions found in construction contracts can include (in alphabetical order):
- Access to the construction site.
- Assignment, rights of third parties and collateral warranties.
- Commissioning.
- Contractor's design.
- Contract sum and adjustment,
- Date for possession, deferment of possession, progress, delays, completion date, suspension of works and termination.
- Dispute resolution procedures and alternative dispute resolution.
- Employer's instructions.
- Force majeure.
- Information release schedule.
- Insolvency.
- Injury, damage and insurance.
- Joint Fire Code.
- Liquidated damages.
- Net contribution clause.
- Partial possession.
- Payment, valuation (including off-site materials), certificates, fluctuations and retention.
- Practical completion.
- Project management and contract administration.
- Quality of works.
- Relevant events (compensation events), extensions of time and loss and expense.
- Sectional completion.
- Statutory obligations.
- Sub-contractors.
- Testing and defects (defects liability period)
- Variations, prime cost sums and provisional sums.
Conditions of contract must be read in conjunction with specification documents, drawings bills of quantities, activity schedules and special conditions. Standard form contracts often comprise suites of contracts with ‘back to back’ subcontracts, consultant appointments and collateral warranties. The use of core conditions with option schedules or supplemental provisions is also now common (see NEC contract).
[edit] Related articles on Designing Buildings
- Addendum.
- Alternative dispute resolution.
- Articles of agreement.
- Common law.
- Competitive procedure with negotiation.
- Condition.
- Construction contract.
- Construction law.
- Contract administrator.
- Contract negotiations.
- Contract strategy.
- Contractual right.
- Delay damages.
- Disallowed cost.
- Escalation.
- Essentials of a contract.
- Excepted risk.
- Extension of time.
- Form of tender.
- Hybrid construction contract.
- Key dates.
- Liquidated damages.
- Loss and expense.
- Modifying clauses in standard forms of contract.
- Named specialist work.
- Negotiated Procedure without Prior Publication NPwPP.
- Outturn cost.
- Payment for extra work.
- Pre-contract management.
- Proprietary information.
- Quantum meruit.
- Right to payment.
- Supply chain management.
- Variation.
- Z clauses.
Featured articles and news
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.
























Comments
this site is indeed very informative👍 worth to spend sometime reading during work break