Hybrid construction contract
Contents |
[edit] Introduction
A contract is a promise or set of promises between two or more parties (the promisor and the promisee) which the law will enforce. In the procurement of construction, contracts are frequently standard, modified or bespoke. They can also be hybrid.
Hybrid contracts are agreements that cover those activities defined under the Housing Grants, Construction and Regeneration Act 1996. This includes construction and non-construction activities.
Section 105 of the Act defines construction activities (classified as a broad range of operations) covered with certain industry-specific exclusions. Non-construction activities are also defined in the Act, but they are only covered under a hybrid contract.
[edit] Hybrid contracts and payment
According to a 6 March 2020 London court ruling, the Act no longer requires hybrid contracts to identify specific construction and non-construction activities. The case of C Spencer Ltd (CSL) v M W High Tech Projects UK Limited (MW) exposed a lack of clarity regarding payments to the contractor (MW) and the subcontractor (CSL) during a project to construct a waste to energy power plant.
This ambiguity around construction and non-construction activities was the cause of court decisions in the past. However, the 2020 ruling stated that the phrase “only in so far as it relates to construction operations" was not necessary with regard to payment terms for non-construction activities in hybrid contracts.
This is clarified further by Simmons+Simmons:
"Hybrid construction contracts are those which include both construction operations covered by the Housing Grants, Construction and Regeneration Act 1996 (the Act) and non-construction operations. The Act has been of great assistance to the construction industry by providing clear and certain provisions in respect of payment applications and the dispute resolution procedure, which has in turn improved cash flow. However, the Act is not as comprehensive as some might have hoped. The use of ‘hybrid contracts’, i.e. those which include both construction operations (as defined by s.104 of the Act) and non-construction operations (not covered by the Act), has resulted in uncertainty.
"The dispute between M W High Tech Projects UK Limited (MW) and C Spencer Ltd (CSL) arose out of this uncertainty. In this case, the court found that payment notices for hybrid construction contracts do not need to separately identify the sums owing for ‘construction operations’, together with the basis of the breakdown, in order to be valid."
[edit] Related articles on Designing Buildings Wiki
- Act.
- Construction contract.
- Construction contract conditions
- Fair payment practices.
- Housing Grants, Construction and Regeneration Act HGRA.
- Modifying clauses in standard forms of construction contract.
- Scheme for Construction Contracts.
[edit] External resources
- England and Wales Court of Appeal (Civil Division) Decisions, C Spencer Ltd v M W High Tech Projects UK Limited [2020 EWCA Civ 331 (06 March 2020)].
- Legislation.gov.uk, Housing Grants, Construction and Regeneration Act 1996.
- Out-Law News, Court of Appeal clarifies UK Construction Act treatment of hybrid contracts, 9 March 2020.
- Simmons + Simmons, Hybrid construction contracts - payment notices.
Featured articles and news
The end of the games but continued calls for action.
From the Commonwealth Association of Architects.
CIOB respond to the government call for evidence
For the Levelling Up, Housing & Communities Committee.
How are buildings and their occupants responding to extreme heat?
BSRIA's Technical Director reflects on recent weather patterns.
Landownership in England in 1909
A national valuation to fund old-age pensions.
The world’s largest Commonwealth memorial to the missing.
Long after the end of the defects liability period.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing in buildings.
Geometric form and buildings in brief
From the simple to the complex.
Understanding the changing nature of insulation
And the UK Government guidelines.
Three year action plan to improve equity, diversity and inclusion
Commitment agreed to by major built environment bodies.
The Construction Route – what needs to change?
Electrical skills, low carbon, high-tech and the building services revolution.
Deep geothermal power possibilities
Ultra-deep drilling with millimeter-wave beam technology.
BSRIA Briefing 2022- From the outside looking in
Looking at the built environment from space.
Competence requirements for principal contractors and designers
BSI standards 8671, 8672 and 8673.
Bringing life to burial grounds.
From failed modernism to twenty-minute neighbourhoods.
Design chill and design freeze
The gates process and change control.
Neuroscience for project success
Why people behave as they do. APM book.