Payment notice for construction contracts
In general terms, 'payment' is the transfer between parties of some form of value (such as funds, services, assets) in an agreed exchange.
In the construction industry, payment can be the source of a great deal of controversy. Not only are the sums involved very large, and the duration of projects very long, but the total amount payable tends to change over time. In addition, contractors, subcontractors and suppliers face considerable risk when pricing construction projects, and optimistic pricing or late payments can quickly cause cash flow problems. Payments are often late, or the source of disputes which can ultimately lead to a breakdown in relationships and even project or business failure.
As a result, The Housing Grants, Construction and Regeneration Act 1996 (also known as the Construction Act) include provisions to ensure that payments are made promptly throughout the supply chain.
These provisions include:
- The right to be paid in interim, periodic or stage payments.
- The right to suspend (or part suspend) performance for non-payment and to claim costs and expenses incurred and extension of time resulting from the suspension.
- Pay when certified clauses are not allowed, and the release of retention cannot be prevented by conditions within another contract.
In addition, there are specific provisions in relation to the procedures for making payments.
- The client must issue a payment notice within five days of the due date for payment, even if no amount is due. Alternatively, if the contract allows, the contractor may make an application for payment, which is treated as if it is the payment notice.
- The client must issue a pay less notice if they intend to pay less than the amount set out in the payment notice, setting out the basis for its calculation.
- The notified sum is payable by the final date for payment.
- If the client (or specified person) fails to issue a payment notice, the contractor may issue a default payment notice. The final date for payment is extended by the period between when the client should have issued a payment notice and when the contractor issued the default payment notice. If the client does not issue a pay less notice, they must pay the amount in the default payment notice.
[edit] Related articles on Designing Buildings
- Advance payment.
- Contract sum.
- Default payment notice.
- Due date.
- Extension of time.
- Fair payment practices.
- Final certificate.
- Housing Grants Construction and Regeneration Act.
- Interim certificate.
- Interim valuation.
- Milestone payment.
- Off site materials.
- Pay less notice.
- Payment.
- Payment period.
- Payment schedule.
- Retention.
- Scheme for construction contracts.
- Small Business, Enterprise and Employment Bill.
[edit] External references
Featured articles and news
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties at 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
























Comments
I have a question:
Say a contractor has issued their valuation, the employer has issued their assessment on the valuation and passed it back to the contractor who has ignored the assessment and not passed comment or acceptance despite chasing from the employer. The five days passes on this day and the following day, the payment notice is issued based on the Employer's Assessment.
Is this acceptable under JCT D&B 2016 contract?
Thanks,
QS
Good information and helpful.
Quick question I have relating to a subcontractor's payment application received. I made an assessment and issued to the subcontractor in error. This was then later revised and payment was made on the revised assessment. How does this stand in terms of final account?
Thanks,
Michael
My gut feeling is that you are entitled to revise an assessment up or down at any time prior to agreeing a final account providing you can support the revision with tangible evidence such as a mathematical or quantification error. Any element of subjective judgment however is more tricky, as a downward adjustment might be interpreted as a negotiating tactic or client pressure.
Clearly the precise answer will depend on the terms of the relevant sub-contract and any terms attached to the valuation...written or oral. But as a general rule interim valuations are just that and can be revised up or down before the final certificate or any binding agreement on any final account. Also it is a general principle of law that mistakes of fact can be amended or may not even be binding as the law recognizes a defence of mistake of fact though not mistake of law and provided no estoppel has arisen.
Hi i am a quantity surveying uni student and i need to write a paper on payments in the construction industry. Is the interim valuation submitted by the contractor and then is valued and certified by the officers in charged OR do the officers in charged just make an interim valuation every month when the time comes??
Thanks.
So, if you owe a company and plan to pay them on 15th of the month and issue a payless on 13th of that same month, is this in order and correct or has it to be no less than 5 days beforehand?
Hi, I have a situation where a payment has been missed. The Contractor has not issued a default payment notice. If her has not issued a formal notice does the Client still have to pay the contractor his stated amount due in his original valuation submission?
In calculating his payment due in his valuation submission he has made an arithmetic error by deducting too much retention. Is his amount due the net amount at the end of the calculation or the gross valuation amount?
I have a question
If I issue an application and the contractor issues a payment notice that is less than the sum applied for does the contractor have to issue a payless notice?
Thanks