Off site materials
It can sometimes be appropriate for the client to pay for items even though they remain ‘off-site’, for example, where a contractor has themselves made a large payment for plant or materials that have yet to be delivered to site, or if the client wishes to ‘reserve’ key items in order to protect the programme. Such items should be agreed in advance and listed in an annex to the contract bills.
Paying for off-site goods or materials can be useful, however, it does put the client at risk, for example if the contractor becomes insolvent and the items are then not delivered, even though payment has been made.
Several mechanisms are available to protect the client:
- The client should check the financial status of the contractor to assess the likelihood of insolvency.
- The client should require proof that the property in the items is vested in the contractor before payment is made. This may include a vesting certificate (certifying that property has passed to the contractor and that the materials will be properly identified, stored and insured), and checking that the suppliers terms and conditions do not include a retention of title clause.
- The items should be set aside, and clearly marked with the client’s details.
- The materials should be 'ready for incorporation'.
- The client should require proof that the materials are insured against specified perils for the period they remain off site.
- If the contractor is part of a larger group, then a guarantee might be required from the holding company.
- An on-demand bond might be required up to the value of the off-site items, with the value of the bond reducing as deliveries to site are made.
- The client might enter into a contract direct with the supplier.
However, none of these methods is fool proof. For example, a vesting certificate may be of limited value in practice, as it is difficult to sue an insolvent contractor. Furthermore, despite best endeavours, items may simply be removed or disappear in the event of insolvency, or if there is a rumour that insolvency might occur. This is particularly true for items that have yet to be fabricated, items that have still to be worked on, or items that are abroad.
In a perfect world, items would be delivered to the site and affixed to the property before payment is made, but where this is not possible, a judgement is necessary to assess the risk to the project, or the potential loss to the client versus the cost of ensuring absolute certainty in relation to off-site goods.
See also: Materials on site.
For legal issues, see Off-site goods and materials - legal issues.
[edit] Related articles on Designing Buildings Wiki
- Advance payment bond.
- Bonds and guarantees.
- BSRIA launches Offsite Construction for Building Services topic guide.
- Construction inventory management.
- Design for Manufacture and Assembly (DfMA).
- How to make projects off-site ready.
- Just in time manufacturing.
- Lead time.
- Logistics management.
- Long lead-time item.
- Materials.
- Materials on site.
- Off-site construction.
- Off-site goods and materials - legal issues.
- Off site, on track.
- On site.
- Platform approach to design for manufacture and assembly.
- Precast.
- Precast flat panel system.
- Protecting and storing rebar.
- Retention of title.
- Site storage.
- Vesting certificate.
Featured articles and news
Or are you capping.
STEM ambassadors needed for ICE CityZen award.
Digital gaming competition for UK students aged 16 to 18.
Heritage protection in England vs Australia.
Fire doors and the Fire Door Inspection Scheme.
Three-quarters of fire doors fail inspections
UN International Day for Biological Diversity, May 22.
The role of geoparks, biospheres and world heritage sites.
BSRIA conference 2022, June 23.
Just one month to go ! Find out more here.
Restoring Broadbent’s Bath House
A new gallery for the University of Huddersfield.
Corruption in the construction industry.
What will it take to stop it ?
To celebrate world bee day 2022 !
Just one month until the changes to part L come into effect.
Not forgetting part F and the new part overheating part O.
Heat Pump demand rises by one quarter.
As energy prices jump up in cost.
With people in the UK from Ukraine.
Industry leader Steve Murray takes on role.
An abundant and versatile building material.
How overheating complicates ending gas in the UK.
600,000 heat pump installations targeted per year by 2028.
Cost planning, control and related articles on DB.
Helping prevent those unwanted outcomes.
ICE debate Public transport - post pandemic.
How has transport changed due to Covid-19 ?
Cross-ventilation in buildings. Do you have it ?
Will you need it ? after June 15 and the new Part O ?
Share your knowledge with the industry.
Create an account and write the first of many articles.
The green jobs delivery group.
CIAT commentary after the first meeting.
Liverpool's world heritage site status
Who is to blame?
Research recommends focussing on portfolio success rather than project success.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.