On-demand bonds in construction
Bonds are a means of protection against the non-performance of the contractor. They are an undertaking by a bondsman or surety to make a payment to the client in the event of non-performance of the contractor. The cost of the bond is usually borne by the contractor, albeit, this is likely to be reflected in the contractor's tender price.
Bonds can be 'on demand' or 'conditional', with conditional bonds requiring that the client provides evidence that the contractor has not performed their obligations under the contract and that they have suffered a loss as a consequence.
With on-demand bonds, the bondsman pays an amount of money set out in the bond immediately on demand in writing without needing to satisfy any preconditions whatsoever (including establishing the contractor’s liability) unless the demand is fraudulent. On-demand bonds tend to be common in international projects but are less normal in the UK were they are generally resisted because of their draconian nature.
Types of bonds that are may be on-demand bonds include:
- Advance payment bonds.
- Off-site materials bonds.
- Bid bonds (or tender bonds).
- Defects liability bonds.
It is important to bear in mind that the name of the document can be misleading and does not necessarily accurately describe the nature of document. It is the content of the document that is key.
In the case of Wuhan Guoyu Logistics Group Co Ltd & Anr v Emporiki Bank of Greece SA (2013), the buyer agreed to provide a payment guarantee from its bank, Emporiki Bank, to Wuhan (the seller), which guaranteed certain of the buyer’s payment obligations under a shipbuilding contract. An earlier court judgment found that the payment guarantee was actually an on-demand bond. The seller demanded payment of an unpaid instalment from the buyer who refused to pay believing the instalment was not due. Consequently, the seller made a demand, in good faith, under the bond from the defendant for the unpaid instalment of the contract price. The defendant paid the money but a subsequent arbitration found that the instalment was not in fact due so the defendant argued that because of the mistake, the monies paid under the bond should be held on trust for it.
The Court of Appeal rejected the defendant’s submissions finding that the bond was an autonomous contract, independent of the contract between the buyer and seller, so that when the seller made a call under the bond, monies were immediately payable as an enforceable cause of action had accrued against the defendant pursuant to the terms of the bond.
If it is at all possible to avoid giving such bonds, they should be resisted where alternative security is available.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach £7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
How to write an inspection and test plan
ITPs for quality control and assurance particular elements.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Winners of the 2024 ASBP Awards
Project, Product and Initiative according to the 6 pillars.