Construction contract strategy
As construction projects involve large amounts of money, a great number of organisations, long durations and great complexity, the development of a clear contract strategy is very important. Adopting the right strategy at the beginning of a project can significantly reduce the risk of problems further down the line.
The contract strategy determines the level of management, design, construction, maintenance, operation and so on that will be required from different parts of the supply chain, and to what extent those services will be integrated. It also determines the level of risk that is allocated to different parties in the supply chain.
Developing an effective contract strategy that supports the client's objectives and allocates risks to those best able to control them, is critical to delivering a project on time, on budget, to the required level of quality and with the fewest possible disputes. For more information see: Procurement route and Standard forms of contract.
This can be particularly difficult on large or complex projects, where the supply chain can be very long and responsibility for performance may cascade down through a plethora of suppliers sometimes unknown to management at the top of the chain. For more information see: Supply chain.
A common problem is that whilst the first and second tiers of the supply chain sign up to fairly onerous agreements, as the chain develops, so the contractual liabilities decrease until suppliers at the end of the chain are often not locked in at all. It is important therefore for all parties to ensure that certain rights and obligations exist not only in their own agreements, but also in the agreements contracting parties have with others. This ensures that the main contractor is not left responsible for all obligations to the employer, that sub-contractors have enforceable rights and that timings are co-ordinated throughout the supply chain. For more information see: Back to back provisions in construction contracts.
In addition, there may be a need for third party agreements such as collateral warranties, which are agreements associated with another 'primary' contract to allow a duty of care to be extended by one of the contracting parties to a third party who is not party to the original contract. For more information see: Collateral warranties.
Other factors that may influence the contract strategy might include:
- The size, complexity, duration and cost of the project.
- Whether the nature of the works required can be described in detail.
- Whether the quantity of works required can be determined.
- The complexity of the supply chain.
- Whether the client requires a single point of responsibility.
- Financing of the project.
- The location of the project (is it in the UK?).
- The experience of the client and contractor with projects of a similar nature.
- Whether the works involve repeating activities, allowing long term relationships to be built up between the parties to the project.
- Whether the client is a single party or multiple parties.
- Risk allocation.
- Market conditions.
- The potential for prefabrication.
- Third party dependencies.
The Construction Playbook, Government Guidance on sourcing and contracting public works projects and programmes Version 1, produced by the Cabinet Office and published in December 2020, states:
'This is where we define the form of contract informed by the commercial model. This includes:
- 'defining critical risk allocation, and ensuring it is properly reflected in the contract
- 'documenting the decisions made earlier on the contractual roles and responsibilities
- 'defining clearly the rights and obligations of each party and the associated contractual processes required to implement the commercial model, manage the contract and deliver the project
'The contract is where all the key elements of the project are drawn together and must
be a fully integrated, consistent suite of documents. It will define what you want to buy (specification), the method and timeframe for delivery, risk allocation and other key
commercial terms (e.g. the payment mechanism and KPIs) and what happens if things go wrong.'
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.