Construction contract strategy
As construction projects involve large amounts of money, a great number of organisations, long durations and great complexity, the development of a clear contract strategy is very important. Adopting the right strategy at the beginning of a project can significantly reduce the risk of problems further down the line.
The contract strategy determines the level of management, design, construction, maintenance, operation and so on that will be required from different parts of the supply chain, and to what extent those services will be integrated. It also determines the level of risk that is allocated to different parties in the supply chain.
Developing an effective contract strategy that supports the client's objectives and allocates risks to those best able to control them, is critical to delivering a project on time, on budget, to the required level of quality and with the fewest possible disputes. For more information see: Procurement route and Standard forms of contract.
This can be particularly difficult on large or complex projects, where the supply chain can be very long and responsibility for performance may cascade down through a plethora of suppliers sometimes unknown to management at the top of the chain. For more information see: Supply chain.
A common problem is that whilst the first and second tiers of the supply chain sign up to fairly onerous agreements, as the chain develops, so the contractual liabilities decrease until suppliers at the end of the chain are often not locked in at all. It is important therefore for all parties to ensure that certain rights and obligations exist not only in their own agreements, but also in the agreements contracting parties have with others. This ensures that the main contractor is not left responsible for all obligations to the employer, that sub-contractors have enforceable rights and that timings are co-ordinated throughout the supply chain. For more information see: Back to back provisions in construction contracts.
In addition, there may be a need for third party agreements such as collateral warranties, which are agreements associated with another 'primary' contract to allow a duty of care to be extended by one of the contracting parties to a third party who is not party to the original contract. For more information see: Collateral warranties.
Other factors that may influence the contract strategy might include:
- The size, complexity, duration and cost of the project.
- Whether the nature of the works required can be described in detail.
- Whether the quantity of works required can be determined.
- The complexity of the supply chain.
- Whether the client requires a single point of responsibility.
- Financing of the project.
- The location of the project (is it in the UK?).
- The experience of the client and contractor with projects of a similar nature.
- Whether the works involve repeating activities, allowing long term relationships to be built up between the parties to the project.
- Whether the client is a single party or multiple parties.
- Risk allocation.
- Market conditions.
- The potential for prefabrication.
- Third party dependencies.
The Construction Playbook, Government Guidance on sourcing and contracting public works projects and programmes Version 1, produced by the Cabinet Office and published in December 2020, states:
'This is where we define the form of contract informed by the commercial model. This includes:
- 'defining critical risk allocation, and ensuring it is properly reflected in the contract
- 'documenting the decisions made earlier on the contractual roles and responsibilities
- 'defining clearly the rights and obligations of each party and the associated contractual processes required to implement the commercial model, manage the contract and deliver the project
'The contract is where all the key elements of the project are drawn together and must
be a fully integrated, consistent suite of documents. It will define what you want to buy (specification), the method and timeframe for delivery, risk allocation and other key
commercial terms (e.g. the payment mechanism and KPIs) and what happens if things go wrong.'
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.