Risk allocation
[edit] Introduction
The term risk can have a number of different meanings in the construction industry, relating to health and safety, project costs, time and so on. In any project, minimising risk is critical to avoid adverse situations such as:
To avoid such scenarios, it is in the interest of all parties on a construction project to aim for risk minimisation, mitigation or elimination.
Risk allocation relates to determining who is responsible for dealing within risks. Normally, risk should be allocated to the party that is best able to manage it or the party best able to control or minimise the impact of the risk. And if in managing the risk also involves bearing its financial cost, there will be greater incentive to take measures to mitigate that risk.
For example, consultants may be best placed to manage design risks, whereas the contractor may be best placed to manage construction risks. The situation becomes more complex when there are unknowns, such as conditions below existing structures; items that have third party dependencies, such as planning permission (particularly on design and build projects); variation in costs over time; items for which responsibility is split between more than one party, and so on.
Investors will be particularly keen to minimise project risks, especially on large, time critical, or complex projects. But this cannot happen until the risks on a project are properly analysed and understood. This may involve developing a risk register, that identifies the likelihood, and severity of a risk, as well as management strategies and responsibility allocation.
For more information see: Risk register.
The Construction Playbook, Government Guidance on sourcing and contracting public works projects and programmes Version 1, produced by the Cabinet Office and published in December 2020 states: 'Inappropriate allocation of risk remains one of the main concerns of suppliers looking to do business with government. It is also one of the most frequent issues raised by the National Audit Office in their audits of government contracts.'
Risk allocation and pricing approaches, guidance note, published by the Government Commercial Function in May 2021 states: ‘Allocation and management of risk is central to all commercial contracts and is one of the core commercial principles informing the approach to contracting with third parties. Each party seeks to minimize its overall risk and maximize its reward, which creates an inherent tension between contracting parties. Government can manage risk by carefully negotiating provisions to transfer or share risk with suppliers. If a supplier is put in a position where they are managing an inappropriate balance of risk then the outcome is highly likely to be poor value for money (a high-risk premium will be loaded into the price), underperformance against the core contract objectives (as supplier focus increasingly shifts to cost cutting) and/or an onerous contract which could ultimately lead to its collapse.’
[edit] Public Private Partnerships (PPPs)
Public Private Partnerships (PPPs) tend to be used on large infrastructure projects where failure to achieve optimal risk allocation could be very serious. PPPs are a very broad range of partnership in which the public and private sectors collaborate for some mutual benefit. This may involve partnerships to deliver policies, services, buildings or infrastructure.
PPPs were first developed in the UK in the 1990s. The idea was that private sector companies could be more efficient at providing certain services than public authorities and so, compared to conventional delivery methods, PPP could deliver better value for money for taxpayers.
One of the key drivers for value for money in PPP delivery models was optimal risk allocation. Most long-term risks in a conventional delivery model are borne by the public partner, whether local or central government. In contrast, a PPP model allows the public partner to transfer liability to the private partner. In this way, government is relieved of shouldering the cost of those risks which it is least able to manage; this includes risks such as construction delays, cost overruns and even long-term maintenance.
Challenges involved with allocating risk in PPP include:
- Government may be better able to shoulder the risk: transferring it to a private agency may be costly and reduce value for money;
- It is difficult to predict what, if any, risks will be faced by the private partner over a 30-40-year maintenance period, and
- Although in principal allocating risk may seem straightforward, in reality it may be challenging.
- Private partners price the risk they are being required to accept, and this can result in PPP contracts becoming expensive in the long term.
For more information see: Public Private Partnerships
[edit] Related articles on Designing Buildings
- Build, own, operate and transfer (BOOT).
- Concession agreement.
- Construction contract.
- Design build finance transfer (DBFT).
- Design build operate (DBO).
- Design risk management.
- Flexibility in PPP Contracts: Best practices from countries where Abertis operates.
- Government Construction Strategy.
- Independent Client Advisers.
- Integrated Supply Team.
- PF2 (successor to PFI).
- Partnership.
- Private Finance Initiative.
- Risk.
- Risk management.
- Risk register.
Featured articles and news
Latest Build UK Building Safety Regime explainer published
Key elements in one short, now updated document.
UKGBC launch the UK Climate Resilience Roadmap
First guidance of its kind on direct climate impacts for the built environment and how it can adapt.
CLC Health, Safety and Wellbeing Strategy 2025
Launched by the Minister for Industry to look at fatalities on site, improving mental health and other issues.
One of the most impressive Victorian architects. Book review.
Common Assessment Standard now with building safety
New CAS update now includes mandatory building safety questions.
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.