Negotiated contract
In order to procure a building, a client will normally have to appoint a number of suppliers. There are a number of procedures that can be adopted to select and appoint suppliers.
- Open procedures.
- Selective procedures.
- Negotiated procedures.
- Serial procedures.
- Framework procedures.
Each has its own advantages and disadvantages which must be considered in relation to the particular objectives and scope of the project.
Some of these procedures involve competitive bidding between multiple contractors, whereas the negotiated procedure involves negotiations with just one pre-selected contractor.
In competitive bidding, a contract is agreed following a tendering process where the award is often made to the cheapest (or best value) tender. The concept of negotiation generally allows more flexibility for the client to select a contractor on a basis other than the lowest bid. Negotiated contracts are generally agreed between a contractor and client that have experience of working together and have a relationship built on trust.
Negotiating with a single supplier may be particularly appropriate for highly-specialist works where there may only be a limited number of potential suppliers, or for extending the scope of an existing contract. It can give the client the confidence of working with a supplier they already know, can reduce the duration and costs of tendering and can allow early supplier involvement.
As the design documents very often have not been completed at the negotiation stage, a cost plus contract or cost reimbursable contract is commonly used for negotiated tenders. This allows for the reimbursement of the contractor for the costs incurred during construction, such as labour, equipment and materials, as well as profit and overhead charges for the management of the project.
However, despite having the advantage of being more flexible, negotiated contracts can also be less attractive for clients who may see the lack of competitive tendering as driving up costs; though it is often the case that a strong working relationship with a contractor whose practice is well-known may more than make up for this over the duration of the project.
Negotiated contracts may not be permitted by some organisations due to the perceived lack of accountability. On public projects, or projects that include a publicly-funded element it may be necessary to advertise contracts.
Advantages:
- Client has flexibility in terms of choosing their preferred contractor.
- Time and cost savings involved in removing the tendering process.
- It can allow early supplier involvement.
- Contractor’s costs and pricing are more transparent as they are not seeking to win the bid purely on the lowest tender.
Disadvantages:
- There are fewer options for the client to choose between and so there may be less innovation.
- The costs may be driven up by the lack of competitive bidding.
- There is a heavy reliance on trust between the parties.
- Unless it is carefully structured and controlled, the negotiation process can create an adversarial atmosphere, even before the contract has been awarded.
- It can be seen as anti-competitive and exclusive, with the potential for ‘cozy’ relationships to develop between the client and the supplier.
[edit] Related articles on Designing Buildings Wiki:
- Back to back provisions in construction contracts.
- Competitive procedure with negotiation.
- Construction contract.
- Contract award.
- Contract negotiation.
- Contract strategy.
- Contractual documents.
- Cost plans.
- Design and build procurement route.
- Essentials of a contract.
- Fixed price construction contract.
- Form of tender.
- Major project construction contract.
- Negotiated Procedure without Prior Publication NPwPP.
- Negotiation techniques.
- Performance specification.
- Tender evaluation.
- Sub-contract.
- Whole-life costs.
[edit] External references
- Construction Management (4th ed.), HALPIN, D.W., SENIOR, B.A., Wiley, (2011)
Featured articles and news
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties at 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.























