Competitive tender
Competitive tendering is a common method of procurement in the construction industry.
A tender is a submission made by a prospective supplier/contractor in response to an invitation to tender. It makes an offer for the supply of goods or services.
Those tendering for a contract are often competing with others, and generally, none of the tenderers are aware of the quotes provided by each other; therefore, they are incentivised to submit their most competitive tender. In this way, it is believed that competition in procurement can add value for the client.
Competitive tendering became increasingly common in the UK in the 1980s, when it was seen as a way of making public organisations open themselves up to bids from a number of different firms. This was intended to increase transparency, drive down costs, and improve the efficiency of state-funded organisations such as central and local government departments.
However, it has been criticised for placing too much emphasis on cost, and not necessarily achieving best value for the client. Competitive tendering can be seen as a 'race to the bottom' and can lead to disputes later in the project as suppliers seek mechanisms to increase their price.
Methods of assessing tenders which consider criteria other than the lowest cost include:
- Best value.
- Auction theory.
- Most Economically Advantageous Tender (MEAT).
- Mean value.
- Exclusion of the extremes.
- Weighted selection criteria.
- Balanced scorecard.
For more information see: Tender evaluation, and Procurement route.
NB The UN Procurement Practitioner's Handbook, produced by the Interagency Procurement Working Group (IAPWG) in 2006 and updated in 2012, defines competitive bidding as: 'A procurement method in which offers from competing suppliers are invited by open advertisement and provided with the scope, specifications, and terms and conditions of the proposed contract as well as the criteria by which the offers will be evaluated. The objectives of competitive bidding are to obtain goods or services at the lowest cost or best value through open and fair competition.'
[edit] Related articles on Designing Buildings Wiki
- Best value.
- Best value procurement.
- Bid evaluation.
- Bid strategies.
- Compliant bid.
- Form of tender.
- Insourcing.
- Most economically advantageous tender (MEAT).
- Non-compliant tender.
- Preferred tenderer.
- Proposals.
- Single-stage tender.
- Tender.
- Tender evaluation.
- Two-stage tender.
- Variant bid.
- Why the lowest price isn't sustainable.
Featured articles and news
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.
Put digitalisation and sustainability at the core of curricula
Project management educators are urged.
Looking back at the influence of climate events
From a designer and writer: 'There are limits to growth but no limits to development'.
Terms, histories, theories and practice.
Biophilic design and natural light
Letting in the light and natural elements into spaces.
APM Programme Management Conference 2024
Strategies for Success.
Residential takes the reins as contract awards even out
Contracts down, but remain above the last quarter of 2023.
Celebrating Eid and the largest mud-brick building.
Barry Kingscote claims prestigious CIOB CMYA Award.
The British Mosque: an architectural and social history
The story of some 1,500 mosques or more in Britain.
Heat pump refrigerants, efficiencies and impacts
R12 to R1270 what are the differences?
Global heat pump market in 2023
Challenging times with positive but modest outlook.
Beyond the infrastructure pipeline
Opportunities and chokepoints.