Variant bids in the construction industry
A tender is a submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods or services. An invitation to tender might be issued for a range of contracts, including; equipment supply, the main construction contract (perhaps including design by the contractor), demolition, enabling works, etc.
In response to an invitation to tender, invited tenderers will submit their tender, which will include their price for supplying the goods or services along with proposals for how the client's requirements will be satisfied if these have been requested.
A variant bid, sometimes referred to as an alternative or non-compliant proposal, may be submitted if the tenderer believes that an alternative to what has been requested by the client could offer better value for money and/or is a more innovative solution. Non-compliant proposals should only be submitted if they have been requested or are explicitly permitted by the client, and they should be accompanied by a compliant proposal. By submitting a compliant bid alongside a variant bid, the client is able to consider them both together and so properly assess the value for money offered by the variant bid.
On public sector projects, a contract notice published under the OJEU regulations must contain a clause indicating whether or not variant bids will be accepted. It can be more difficult to tell whether or not a variant bid will be accepted on a private sector tender. If it is not specified one way or the other in the contract notice, there may be guidance in the appropriate tender documents (i.e. in the instructions to tenderers or specification). Otherwise, the only way to ascertain whether it will be permitted may be to contact the client directly for clarification.
Tenderer submissions should clearly state if they are returning a variant bid and, if appropriate, provide clarity on which specification items the variant has deviated from, as well as how the required outcomes will be achieved. The tenderer must persuade the buyer that the alternative proposal does not increase the level of risk and convince them of the potential benefits. The tenderer must be prepared to provide further details if necessary and to answer questions regarding the variations which are likely to follow the submission.
A variant bid may not be allowed if the contracting authority believes it would make the tendering exercise less equitable and fair as it could leave them open to challenge from an unsuccessful tenderer if they were to award the contract to the variant bid. It might also not be allowed due to the extra time and effort required to assess the bid alongside the others that may be compliant with the specifications. Since set outputs are usually established to enable fair comparison of submitted tenders, a variant bid may result in different outputs, as well as different prices, rates, and so on. Therefore, the client may, for the sake of ease and reduced risk, decide that all tenderers must submit compliant bids.
However, clients may want to allow variant bids on the basis that it may result in better value for money, innovation and a better design outcome that draws upon the expertise and experience of the bidders. They might also be concerned that bidders who may otherwise successfully meet the specified outcomes could be deterred from tendering if they are unable to submit certain, perhaps minor, variations.
NB The Chartered Institute of Procurement & Supply (CIPS) Glossary of procurement terms, defines a variant bid as: ‘A tender offer that does not quite match the specification of contract terms, but has been authorised as a secondary offer from a supplier. It is used to see if the proposed specification and contract terms can be improved upon via competitive offers and must be authorised by the purchaser as part of the invitation to tender.’
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.