Enabling works for construction
Enabling works is a generic description for site preparation works that might take place prior to work under the main construction contract.
This could include:
- Demolition.
- Site clearance.
- Tree protection.
- Diversion and/or disconnection of existing site services.
- Geotechnical and exploratory ground investigation.
- Decoupling from existing buildings.
- Decontamination.
- Ground improvement and/or compaction.
- Excavation of known below-ground obstructions.
- Survey work.
- Creation of access routes.
- Perimeter fencing and security provisions.
- Work to neighbouring buildings.
- Discharging planning conditions that must be satisfied prior to construction commencing.
- Historical architectural investigation fieldwork.
- Access ramps.
- Signage provisions.
- Provision of statutory utilities to the site.
Enabling works might be preceded by 'mobilisation' activities, carried out after the client has selected the contractor, but before works commence on site. These are preparatory activities, such as; preparing method statements, arranging road closures, placing necessary sub-contracts, and so on. See Mobilisation for more information.
NB: NRM1: Order of cost estimating and cost planning for capital building work, defines enabling works as:
'...works executed ahead of the main building contract. Enabling works are employer and/or project team specified works, which might include a mixture of facilitating works and new building works (e.g. site preparatory works such as major demolition, removal of contaminated materials, reptile mitigation measures, and soil stabilisation; together with new sewers, new access road, new drainage, new retaining walls, and minor new building works).'
This is as opposed to facilitating works, which NRM1 defines as:
‘…all components measured and incorporated in group element 0 (i.e. Facilitating works). Includes specialist works which, normally, need to be completed before any building works can commence (e.g. major demolition works, soil stabilisation works and or temporary diversion of mains drainage).’
Advantages of having an enabling works contract:
- On site sooner.
- Can saves time and money.
- Could have a specialist contractor for carrying out that particular type of works eg. demolition.
Disadvantages:
- The cost and time to make up two separate contracts
- Process complexity involved in making up two separate contracts
- If there are two different contractors; liability and hand-over issues.
[edit] Related articles on Designing Buildings
Featured articles and news
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.