Enabling works for construction
Enabling works is a generic description for site preparation works that might take place prior to work under the main construction contract.
This could include:
- Demolition.
- Site clearance.
- Tree protection.
- Diversion and/or disconnection of existing site services.
- Geotechnical and exploratory ground investigation.
- Decoupling from existing buildings.
- Decontamination.
- Ground improvement and/or compaction.
- Excavation of known below-ground obstructions.
- Survey work.
- Creation of access routes.
- Perimeter fencing and security provisions.
- Work to neighbouring buildings.
- Discharging planning conditions that must be satisfied prior to construction commencing.
- Historical architectural investigation fieldwork.
- Access ramps.
- Signage provisions.
- Provision of statutory utilities to the site.
Enabling works might be preceded by 'mobilisation' activities, carried out after the client has selected the contractor, but before works commence on site. These are preparatory activities, such as; preparing method statements, arranging road closures, placing necessary sub-contracts, and so on. See Mobilisation for more information.
NB: NRM1: Order of cost estimating and cost planning for capital building work, defines enabling works as:
'...works executed ahead of the main building contract. Enabling works are employer and/or project team specified works, which might include a mixture of facilitating works and new building works (e.g. site preparatory works such as major demolition, removal of contaminated materials, reptile mitigation measures, and soil stabilisation; together with new sewers, new access road, new drainage, new retaining walls, and minor new building works).'
This is as opposed to facilitating works, which NRM1 defines as:
‘…all components measured and incorporated in group element 0 (i.e. Facilitating works). Includes specialist works which, normally, need to be completed before any building works can commence (e.g. major demolition works, soil stabilisation works and or temporary diversion of mains drainage).’
Advantages of having an enabling works contract:
- On site sooner.
- Can saves time and money.
- Could have a specialist contractor for carrying out that particular type of works eg. demolition.
Disadvantages:
- The cost and time to make up two separate contracts
- Process complexity involved in making up two separate contracts
- If there are two different contractors; liability and hand-over issues.
[edit] Related articles on Designing Buildings
Featured articles and news
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”