Enabling works for construction
Enabling works is a generic description for site preparation works that might take place prior to work under the main construction contract.
This could include:
- Demolition.
- Site clearance.
- Tree protection.
- Diversion and/or disconnection of existing site services.
- Geotechnical and exploratory ground investigation.
- Decoupling from existing buildings.
- Decontamination.
- Ground improvement and/or compaction.
- Excavation of known below-ground obstructions.
- Survey work.
- Creation of access routes.
- Perimeter fencing and security provisions.
- Work to neighbouring buildings.
- Discharging planning conditions that must be satisfied prior to construction commencing.
- Historical architectural investigation fieldwork.
- Access ramps.
- Signage provisions.
- Provision of statutory utilities to the site.
Enabling works might be preceded by 'mobilisation' activities, carried out after the client has selected the contractor, but before works commence on site. These are preparatory activities, such as; preparing method statements, arranging road closures, placing necessary sub-contracts, and so on. See Mobilisation for more information.
NB: NRM1: Order of cost estimating and cost planning for capital building work, defines enabling works as:
'...works executed ahead of the main building contract. Enabling works are employer and/or project team specified works, which might include a mixture of facilitating works and new building works (e.g. site preparatory works such as major demolition, removal of contaminated materials, reptile mitigation measures, and soil stabilisation; together with new sewers, new access road, new drainage, new retaining walls, and minor new building works).'
This is as opposed to facilitating works, which NRM1 defines as:
‘…all components measured and incorporated in group element 0 (i.e. Facilitating works). Includes specialist works which, normally, need to be completed before any building works can commence (e.g. major demolition works, soil stabilisation works and or temporary diversion of mains drainage).’
Advantages of having an enabling works contract:
- On site sooner.
- Can saves time and money.
- Could have a specialist contractor for carrying out that particular type of works eg. demolition.
Disadvantages:
- The cost and time to make up two separate contracts
- Process complexity involved in making up two separate contracts
- If there are two different contractors; liability and hand-over issues.
[edit] Related articles on Designing Buildings
Featured articles and news
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach £7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
How to write an inspection and test plan
ITPs for quality control and assurance particular elements.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Winners of the 2024 ASBP Awards
Project, Product and Initiative according to the 6 pillars.