Variant bids in the construction industry
A tender is a submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods or services. An invitation to tender might be issued for a range of contracts, including; equipment supply, the main construction contract (perhaps including design by the contractor), demolition, enabling works, etc.
In response to an invitation to tender, invited tenderers will submit their tender, which will include their price for supplying the goods or services along with proposals for how the client's requirements will be satisfied if these have been requested.
A variant bid, sometimes referred to as an alternative or non-compliant proposal, may be submitted if the tenderer believes that an alternative to what has been requested by the client could offer better value for money and/or is a more innovative solution. Non-compliant proposals should only be submitted if they have been requested or are explicitly permitted by the client, and they should be accompanied by a compliant proposal. By submitting a compliant bid alongside a variant bid, the client is able to consider them both together and so properly assess the value for money offered by the variant bid.
On public sector projects, a contract notice published under the OJEU regulations must contain a clause indicating whether or not variant bids will be accepted. It can be more difficult to tell whether or not a variant bid will be accepted on a private sector tender. If it is not specified one way or the other in the contract notice, there may be guidance in the appropriate tender documents (i.e. in the instructions to tenderers or specification). Otherwise, the only way to ascertain whether it will be permitted may be to contact the client directly for clarification.
Tenderer submissions should clearly state if they are returning a variant bid and, if appropriate, provide clarity on which specification items the variant has deviated from, as well as how the required outcomes will be achieved. The tenderer must persuade the buyer that the alternative proposal does not increase the level of risk and convince them of the potential benefits. The tenderer must be prepared to provide further details if necessary and to answer questions regarding the variations which are likely to follow the submission.
A variant bid may not be allowed if the contracting authority believes it would make the tendering exercise less equitable and fair as it could leave them open to challenge from an unsuccessful tenderer if they were to award the contract to the variant bid. It might also not be allowed due to the extra time and effort required to assess the bid alongside the others that may be compliant with the specifications. Since set outputs are usually established to enable fair comparison of submitted tenders, a variant bid may result in different outputs, as well as different prices, rates, and so on. Therefore, the client may, for the sake of ease and reduced risk, decide that all tenderers must submit compliant bids.
However, clients may want to allow variant bids on the basis that it may result in better value for money, innovation and a better design outcome that draws upon the expertise and experience of the bidders. They might also be concerned that bidders who may otherwise successfully meet the specified outcomes could be deterred from tendering if they are unable to submit certain, perhaps minor, variations.
NB The Chartered Institute of Procurement & Supply (CIPS) Glossary of procurement terms, defines a variant bid as: ‘A tender offer that does not quite match the specification of contract terms, but has been authorised as a secondary offer from a supplier. It is used to see if the proposed specification and contract terms can be improved upon via competitive offers and must be authorised by the purchaser as part of the invitation to tender.’
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.