Back-to-back provisions in construction contacts
|
The term ‘back-to-back’ refers to the replication of contractual terms through the supply chain.
As contractors increasingly sub-contract much of their work to others, so the construction supply chain has become longer and more complex. It is important for all parties to ensure that certain rights and obligations exist not only in their own agreements, but also in the agreements contracting parties have with others. This ensures that the main contractor is not left responsible for all obligations to the employer, that sub-contractors have enforceable rights and that timings are co-ordinated throughout the supply chain.
Typically, descriptions of back-to-back requirements focus on the relationship between the employer, contractor and sub-contractors, but they apply equally to sub-sub-contractors, suppliers, consultants and sub-consultants.
In its strictest form, back-to-back refers not just to the replication of contractual rights and obligations in different levels of contract, but to a requirement that the terms of agreement at one level are included in agreements at lower levels.
This is a very complex process that requires careful consideration and drafting to ensure the correct terms - and only those terms - are passed on, that they are phrased appropriately and that requirements, and in particular timings, are properly co-ordinated.
Back-to-back provisions can be created by:
- Including reference to terms in the main contract to be included, excluded or varied in a sub-contract. This requires very careful checking as it can be difficult to identify every clause that is relevant and it results in a need to cross-reference between agreements; it also requires that sub-contractors have access to higher tier contracts.
- Drafting bespoke sub-contracts that reflect the rights and obligations in the main contract. While the end result is neater and simpler to understand than referencing, equal care needs to be taken in drafting.
- Using standard form contracts that already include back-to-back provisions in main contracts and sub-contracts.
Key aspects of construction contracts that might require back-to-back provisions include:
- Key dates, notification periods and other time-related procedures. For example, claims can fail if the timing of the sub-contract claims procedure does not give the main contractor sufficient time to make a claim themselves.
- Enforcement of dispute resolution findings and the right to participate in proceedings.
- A requirement that valid claims must be passed on.
- Allocation of liability for liquidated damages.
- Entitlement to extensions of time.
- Entitlement to loss and expense.
- Information and reporting requirements.
- The definition of completion.
- Obligations to achieve a certain quality and to comply with certain standards.
- Indemnities.
- Collateral warranties.
- Suspension and termination rights.
- Design responsibilities.
- Transfer of copyright.
The Housing Grants Construction and Regeneration Act prevents the inclusion of pay-when-paid or pay-when-certified clauses, and the release of retention (i.e retention monies) cannot be prevented by conditions within another contract.
[edit] Related articles on Designing Buildings
- Building Users' Insurance Against Latent Defects.
- Collateral warranties.
- Concession Contracts Regulations.
- Construction contracts.
- Contra charges.
- Flow-down term.
- Housing Grants Construction and Regeneration Act.
- Liberty Mercian Limited v Cuddy Civil Engineering Limited and others.
- Pay when paid.
- Proprietary information.
- Sub-consultants.
- Sub-contracts.
- Z clauses.
Featured articles and news
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.
A brief run down of changes intentions from April in an onwards.
Reslating an ancient water mill
A rare opportunity to record, study and repair early vernacular roofs.
CIOB Apprentice of the Year 2025/26
Construction apprentice from Lincoln Mia Owen wins this years title.
Insulation solutions with less waste for a circular economy
Rob Firman, Technical and Specification Manager, Polyfoam XPS explains.
Recycled waste plastic in construction
Hierarchy, prevention to disposal, plastic types and approaches.
UK Net Zero Carbon Buildings Standard V1 published
Free-to-access technical standard to enable robust proof of a decarbonising built environment.
Prostate Cancer Awareness Month
Why talking about prostate cancer matters in construction.
The Architectural Technology podcast: Where it's AT
Catch up for free, subscribe and share with your network.
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
























