Contract claims procedure
Contents |
[edit] Introduction
The process for making claims under a construction contract typically involves several key steps to ensure they are made in accordance with the contract terms and that they are properly documented and substantiated. This article presents an outline of common procedures, but ultimately the process required will depend on the exact wording of the contract and the application of relevant legislation such as the Housing Grants, Construction and Regeneration Act.
[edit] Identify the basis for the claim
Claims can arise from a number of situations, such as:
- Variations or changes to the work scope.
- Delays and disruptions.
- Unforeseen site conditions.
- Non-payment or late payment.
- Breach of contract terms.
For more information see: Contract claims.
[edit] Review the contract
Carefully review the construction contract to understand:
- The types of claims that can be made.
- The notice requirements.
- The time frames for submitting claims.
- The specific procedures for making a claim.
- The documentation required.
[edit] Notification
Most contracts require prompt notice of a claim. This notice should include:
[edit] Document the claim
This may include:
- Detailed records of the work performed.
- Correspondence (emails, letters).
- Site diaries and logs.
- Photographs and videos.
- Statements from witnesses.
- Schedules and programs.
[edit] Prepare the claim submission
Prepare a formal claim document, which typically includes:
- An introduction and summary of the claim.
- A detailed description of the events leading to the claim.
- The contractual basis for the claim (citing relevant contract clauses).
- Supporting documentation and evidence.
- Calculations of the claim value (e.g., costs incurred, delay impacts).
[edit] Submit the claim
Submit the claim to the other party (e.g., the employer, main contractor) in accordance with the contract’s procedures. Ensure that the submission is timely and includes all necessary documentation.
After submitting the claim, there may be a period of negotiation and discussion. The goal is to reach an agreement on the validity and value of the claim. This may involve:
- Meetings and discussions between the parties.
- Clarification and provision of additional information if requested.
- Adjustments to the claim based on feedback.
If the claim is not resolved through negotiation, the contract will typically provide for dispute resolution mechanisms, which may include mediation, adjudication (a statutory process under the Housing Grants, Construction and Regeneration Act 1996), arbitration or litigation.
[edit] Related articles on Designing Buildings
- Adjudication.
- Alternative dispute resolution.
- Arbitration.
- Contract claims.
- Construction contract.
- Dispute avoidance.
- Dispute resolution.
- Disruption claims in construction.
- Evaluation of claims.
- Housing Grants, Construction and Regeneration Act.
- How to prepare a claim for an extension of time.
- Mediation.
- Scheme for Construction Contracts.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.