Set off in construction contracts
Set off (sometimes called contra charging) is a legal process by which party A defends a claim brought by party B, by A setting off in extinction or diminution of B’s claim, claims which A alleges against B.
For example:
- A client might reclaim the cost of water damage to their property caused by a contractor fitting out the floor above the damaged area.
- A contractor might set off costs against a sub-contractor that caused damage to finished work adjacent to the working area of the sub-contractor.
- In the case of late completion a client might set off the appropriate amount of liquidated and ascertained damages in accordance with the contract.
Whilst set off is often accompanied by a counterclaim it is to be distinguished in that set off cannot, unlike a counterclaim, give rise to a positive balance of claim.
Set off rights can either be contractual, equitable or in the case of insolvency, statutory.
Contractual set off will depend on the wording of the agreement between the parties. It is possible for contractual set off rights to extend to a wide range of different contracts, but the wording must be clear. Equitable set off arises by operation of law if there is sufficient proximity and connection between the parties (e.g. the same parties, site and project). A recent statement of the law of equitable set off is given in the Court of Appeal judgement in Geldof Metaalconstructie NV v Simon Carves Ltd [2010].
If a contracting party becomes insolvent, the Insolvency Act 1986 Section 323 (bankruptcy) and the Insolvency Rules Rule 4.90 (liquidation) provide for a statutory set off known as ‘mutual credits and mutual debits’.
This statutory set off requires account to be taken between the insolvent party and the proving creditor of mutual debts, mutual credits and mutual dealings arising before the insolvency which are then set off leaving only the balance, if any, provable in the insolvency. This is, of course, only fair as otherwise the creditor would be 100% liable on debts due to the insolvent and only receive the relevant distribution (often nothing) on debts owed by the insolvent.
In construction contracts, rights of set off and withholding payments are regulated by the Housing Grants, Construction and Regeneration Act 1996 Part II Section 111, amended, with effect from October 2011, by the Local Democracy, Economic Development and Construction Act 2009 Part 8 Section 144. These Acts regulate the contents and prescribed periods for 'pay less' notices which must be served if a party wishes to deduct sums from amounts otherwise due under the contract.
Adjudication procedures constrain the effect of set off to preserve the public policy of adjudication that it should be a relatively speedy interim solution. In M J Gleeson Group Plc v Devonshire Green Holding Ltd [2004], the court held that a respondent could not set off claims arising after the commencement of the adjudication to avoid payment of a sum awarded by the adjudicator.
See also Section 111 (4) Housing Grants, Construction and Regeneration Act.
[edit] Related articles on Designing Buildings Wiki
- Abatement.
- Adjudication.
- Alternative dispute resolution.
- Contract.
- Contract conditions.
- Counterclaim.
- Housing Grants, Construction and Regeneration Act.
- Liquidated and ascertained damages.
- Mediation.
- Scheme for Construction Contracts.
[edit] External references
Featured articles and news
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Comments