Concession Contracts Regulations
Contents |
[edit] Introduction
A concession contract is a contract between a company and a government; or between a contracting authority/utility company and an economic operator/other property owner to operate a business in a particular location.
A ‘contracting authority’ is defined as a ‘state, regional or local authority’ while a utility is defined as an entity that pursues one of the activities listed in Schedule 2.
Payment (or consideration) may come from the contractor exploiting the contractual right to profit from the arrangement or else by exploiting the contract for profit plus a payment from the contracting authority.
Under such contracts, the operating risk of exploiting the contract falls on the contractor, i.e. they must face the vagaries of the market whether connected to demand or supply or both. Any losses incurred by the concessionaire in these respects must be accepted. Furthermore, it is understood from the outset that there is no guarantee they will recoup their investments or the costs involved in operating the concession under normal operating conditions.
A typical example of a concession that might be the subject of a contract is a car park built on local authority-owned land, where the contract will be between the local authority (contracting authority) and the car-park operator. Either of these may involve a transfer of ownership to the contracting authority at some point in the future.
[edit] The Regulations
The Concession Contracts Regulations 2016 (“CCR 2016”) came into force on April 18 for concessions advertised in the Official Journal of the European Union (OJEU) (this may change after the UK leaves the EU). The regulations cover England, Wales and Northern Ireland, and regulate the process of procuring concessions’ contracts, with reference to contracts advertised in the journal by contracting authorities and utilities (e.g water companies power suppliers etc). They do not cover projects started before April 18 2016.2
Regulation 8 of the CCR 2016 suite of regulations stipulates a maximum threshold of €5,225,000. The regulation contains a defined procedure that sets out how to calculate the potential value of the concession. The value is determined by the contracting authority estimating the total amount turned over by the contractor/concessionaire over the contract term by operating the services that are the subject of the contract.
[edit] The two types of concession contract:
- Works concession contract – i.e for the execution, or design and execution, of, and
- Services concession contract—i.e for the provision and management of services (other than the execution of works).
[edit] Arrangements not considered concession contracts include:
- Outsourcing contracts or privatisation;
- Financing works or services e.g a grant;
- If there is a choice for customers between providers delivering the same service;
- A land lease contract;
- Where an economic operator has a right to exploit public domains such as maritime, inland ports or the airport sector as these may involve general conditions for their use without the need to procure specific works and services;
- Granting the right of way covering the use of public immovable property, fixed lines or networks;
- Where no payments are made but the contract is remunerated on the basis of regulated tariffs calculated to cover all costs and investments borne by the concessionaire for providing the service. The concessionaire must be exposed to a potential loss;
- Where the contracting authority or utility relieves the concessionaire of any loss by guaranteeing minimal revenue equal or higher to the investment made and the costs the economic operator has to incur, and
- Where sector-specific regulations eliminate the risk by providing a guarantee to the concessionaire of breaking even in terms of the investments and costs incurred for operating the concession.
The full list of what is not regarded as a concession contract can be found here:
[edit] Related articles on Designing Buildings Wiki
- Back-to-back provisions in construction contacts.
- Collateral warranties.
- Construction manager.
- Contract.
- Design, build, manage contractor.
- Management contract.
- Management contracting - pros and cons.
- Operative.
- Procurement route.
- Sub-agent.
- Sub-contractor.
- Trade contractor.
- Types of contractor.
- Work package contractor.
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.