Fixed price construction contract
Lump sum (or stipulated sum) contracts are sometimes referred to as ‘fixed price’ or 'firm price' contracts, although strictly this is not correct.
On a lump sum contract, a single ‘lump sum’ price is agreed before the works begin. If the actual cost of the works exceeds the agreed price, then the contractor must bear the additional expense. If on the other hand the cost of the works is less than the agreed price, the contractor will benefit from the savings.
This is unlike a guaranteed maximum price contract, where the contractor bears any additional costs above the guaranteed maximum price, but if the cost is lower than the guaranteed maximum price, then savings may go to the client, to the contractor or are shared. An extension of this is the target cost contract, where there is a ‘pain / gain’ agreement allowing the client and contractor to share both additional costs and savings.
However, lump sum contracts tend not to be fixed at all, but allow the price to change under certain circumstances:
- Variations: These are changes in the nature of the works. Most contracts will contain provision for the architect or contract administrator to issue instructions to vary the design, quantities, quality, sequence or working conditions.
- Relevant events: A relevant event may be caused by the client (for example failure to supply goods or instructions), or may be a neutral event (such as exceptionally adverse weather) and may result in a claim for loss and expense by the contractor.
- Provisional sums: An allowance for a specific element of the works that is not defined in enough detail for tenderers to price.
- Fluctuations: A mechanism for dealing with inflation on projects that may last for several years, where the contractor tenders based on current prices and then the contract makes provisions for the contractor to be reimbursed for price changes over the duration of the project.
- Payments to nominated sub-contractors or nominated suppliers.
- Statutory fees.
- Payments relating to opening-up and testing the works.
A truly 'fixed' price contract would not necessarily be in the interests of the client as it would require that the contractor price risks over which they may have no control, and which might not arise.
[edit] Firm price contract
The Code of Estimating Practice, seventh edition, published by the Chartered Institute of Building (CIOB) in 2009 defines a fixed price contract as, ‘…a contract where the price is agreed and fixed before construction starts’.
It suggests that a firm price contract is, ‘…a contract where the prices is not subject to fluctuations during the construction period’, where fluctuations are, ‘…the increase or decrease in cost of labour, plant, materials and/or overheads costs that may occur during a contract.’
[edit] Related articles on Designing Buildings
- Code of Estimating Practice.
- Evaluation of claims.
- Fixed charge.
- Fluctuations.
- Force account work.
- Guaranteed maximum price.
- Lump sum contract.
- Lump sum contract - pros and cons.
- Negotiated contract.
- Open-book accounting.
- Price.
- Procurement route.
- Provisional sums.
- Relevant events.
- Target cost contract.
- Time and material contract (T&M).
- Traditional contract - pros and cons.
- Variations.
Featured articles and news
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach £7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
How to write an inspection and test plan
ITPs for quality control and assurance particular elements.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Winners of the 2024 ASBP Awards
Project, Product and Initiative according to the 6 pillars.