Furniture fixtures and equipment FF&E
FF&E refers to the procurement of furniture, fixtures and equipment.
This might be procured separately to the main construction contract (or elements of them), particularly by clients that already have systems in place for procuring fixed and loose furniture, fittings and equipment; for example schools, universities, or hospitals.
It is very important under such circumstances to define very clearly which contract every element of FF&E is within (for example, there may still be unusual or large items that it may be more sensible to procure under the main contract).
It is also important to ensure that any building work required for the installation of such items is identified and procured, that any services required (such as power or drainage) are identified and that the installation of FF&E is properly integrated into the main contract.
Requirements that affect the main contract might include:
- Built-in equipment requiring mechanical or electrical connections, such as fume cupboards or drinks stations. A description of built-in equipment should include; location, size, and requirements for power, air, water, drainage and telecommunications connection.
- Built-in equipment that does not require services such as cupboards or shelving. These should be described in terms of their location and size.
- Stand-alone loose furniture and equipment requiring services, such as washing machines, coffee machines and scanning equipment in hospitals. These should be described in terms of their location, size, and requirements for power, air, water, drainage and telecommunications connection.
- Stand-alone loose furniture and equipment not requiring services such as tables and chairs. These should be described in terms of their location and size.
It is also important that any elements that are outside of the main contract are included in the client's cost plans.
FF&E can be procured from specialist suppliers, or suppliers with whom the client already has a long term relationship. This may include maintenance arrangements. Some elements may be specially designed by FF&E designers or sourced by FF&E consultants. There is also a need for a carefully managed FF&E inventory and logistical planning to ensure items are available on-site at the right time.
In managing the procurement of FF&E, consultants take on the complicated and time-consuming task of coordinating with the design team, external vendors and internal departments for the following:
- Programming and planning.
- Sourcing.
- Project procurement strategy and risk analysis.
- Request for proposal (RFP) document development.
- RFP process management.
- Contract negotiation and buy-out.
- Order expediting and tracking.
- Installation, product acceptance and close-out.
For more information, see FF&E consultant.
[edit] Related articles in Designing Buildings
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings for people to come home to... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”