Engineering Procurement and Construction Management Contract
Engineering Procurement and Construction Management contracts (EPCM contracts), like Engineering Procurement and Construction contracts (EPC contracts) are similar to design and build contracts, in that there is a single point of responsibility for the design and construction of the project, but generally, the client has less say over the design of the project than on a design and build project, and the contractor takes more risk.
However, unlike an EPC contract, on an EPCM contract the client employs the necessary trade contractors to construct the works. The 'contractor' designs the project, and then acts as a construction manager, co-ordinating the procurement process and then managing the trade contractors. Effectively they are performing the roll of a consultant during the construction phase.
This might be appropriate where the client wishes to retain a degree of control over the procurement process, for example if there is uncertainty about the exact scope or nature of the works required when the procurement process begins. This can be used to accelerate construction by enabling some parts of the works to begin (for example piling) whilst the design of other parts of the works continues.
As the client contracts the trade contractors themselves, they require greater expertise than they would on an EPC contract.
Generally, EPCM contracts are used on engineering and infrastructure projects, where the aesthetics of design might be considered less important to the client than performance and cost certainty.
[edit] Related articles on Designing Buildings
- Contract.
- Contract conditions.
- Construction management.
- EPC contract.
- Procurement route.
- What is an EPC contract?
[edit] External references
- Project Procurement Management Processes
- Skills Funding Agency: Procurement routes.
- CABE: Procurement routes.
- PACE Guidance on the Appointment of Contractors and Consultants for a detailed analysis of the pros and cons of various procurement routes.
- nbs: National Construction Contracts and Law Survey 2012.
- JCT: Deciding on the appropriate JCT contract.
Featured articles and news
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.