Engineering Procurement and Construction Management Contract
Engineering Procurement and Construction Management contracts (EPCM contracts), like Engineering Procurement and Construction contracts (EPC contracts) are similar to design and build contracts, in that there is a single point of responsibility for the design and construction of the project, but generally, the client has less say over the design of the project than on a design and build project, and the contractor takes more risk.
However, unlike an EPC contract, on an EPCM contract the client employs the necessary trade contractors to construct the works. The 'contractor' designs the project, and then acts as a construction manager, co-ordinating the procurement process and then managing the trade contractors. Effectively they are performing the roll of a consultant during the construction phase.
This might be appropriate where the client wishes to retain a degree of control over the procurement process, for example if there is uncertainty about the exact scope or nature of the works required when the procurement process begins. This can be used to accelerate construction by enabling some parts of the works to begin (for example piling) whilst the design of other parts of the works continues.
As the client contracts the trade contractors themselves, they require greater expertise than they would on an EPC contract.
Generally, EPCM contracts are used on engineering and infrastructure projects, where the aesthetics of design might be considered less important to the client than performance and cost certainty.
[edit] Related articles on Designing Buildings
- Contract.
- Contract conditions.
- Construction management.
- EPC contract.
- Procurement route.
- What is an EPC contract?
[edit] External references
- Project Procurement Management Processes
- Skills Funding Agency: Procurement routes.
- CABE: Procurement routes.
- PACE Guidance on the Appointment of Contractors and Consultants for a detailed analysis of the pros and cons of various procurement routes.
- nbs: National Construction Contracts and Law Survey 2012.
- JCT: Deciding on the appropriate JCT contract.
Featured articles and news
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherit assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.

















