Front-loaded costs
The term ‘front-loaded’ refers to costs that are applied disproportionately to elements of the work that take place early on during a project or part of a project.
Suppliers may front-load costs (or prices in bids) in order to maximise their revenue early in a project by assigning overstated values to the preliminary elements of the work. For example, a contractor might front-load costs for preliminary construction work such as services diversions, demolition, setting out, groundworks, piling, and so on.
Front-loading costs can help reduce a supplier's risk on a project, by improving their cash flow and ensuring that maximum payments are received on projects that might not proceed to completion. However, making payments in excess of the value of work completed puts the client under greater financial pressure early in the project and also at greater risk if the project does not proceed, or if a supplier becomes insolvent or has to be replaced. It can also act as a disincentive for suppliers to keep to time schedules, as they may have already completed the most profitable parts of the works.
Front loading can be avoided by detailed cost planning and cash flow projection during the design development and tender stages of a project, giving the client a clear idea of how much they should be expected to pay at different stages. Tender assessment should then allow comparisons to be made between competing bids to determine whether individual tenderers have submitted excessive prices for certain aspects or stages of the works. During the construction phase, there should be careful assessment of applications for payment to ensure that the amounts paid do not exceed the value of the works completed.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.