Front-loaded costs
The term ‘front-loaded’ refers to costs that are applied disproportionately to elements of the work that take place early on during a project or part of a project.
Suppliers may front-load costs (or prices in bids) in order to maximise their revenue early in a project by assigning overstated values to the preliminary elements of the work. For example, a contractor might front-load costs for preliminary construction work such as services diversions, demolition, setting out, groundworks, piling, and so on.
Front-loading costs can help reduce a supplier's risk on a project, by improving their cash flow and ensuring that maximum payments are received on projects that might not proceed to completion. However, making payments in excess of the value of work completed puts the client under greater financial pressure early in the project and also at greater risk if the project does not proceed, or if a supplier becomes insolvent or has to be replaced. It can also act as a disincentive for suppliers to keep to time schedules, as they may have already completed the most profitable parts of the works.
Front loading can be avoided by detailed cost planning and cash flow projection during the design development and tender stages of a project, giving the client a clear idea of how much they should be expected to pay at different stages. Tender assessment should then allow comparisons to be made between competing bids to determine whether individual tenderers have submitted excessive prices for certain aspects or stages of the works. During the construction phase, there should be careful assessment of applications for payment to ensure that the amounts paid do not exceed the value of the works completed.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.