Without quantities
Contents |
[edit] Introduction
The term ‘without quantities’ refers to a construction contract or tender documents that do not include specific measured quantities of the items of work identified by the drawings and specifications. It can be used on projects where it is not possible to prepare a bill of quantities (BOQ) at the time of tendering. This might be because the design is progressed enough for tendering purposes but not firm enough to provide accurate quantities.
Smaller projects, or alteration work may also be tendered without quantities, for example where a schedule of works is prepared allowing the pricing of items, such as builders' work and fixing schedules. For more information see: Schedule of works.
An intermediate position between the two approaches is ‘approximate quantities’. For more information see: Approximate quantities.
[edit] Contract features
Tendering on the basis of “without quantities” can allow selection of the contractor and so expedite the project program. Generally, the design will be relatively complete, but may be insufficient time or information to determine the quantities. Drawings, specifications and schedules will generally form the key contract documents if projects are procured in this way.
Procuring ‘without quantities’ will result in a lump sum contract. There will be no re-measurement required and it can simplify the valuation process. This might initially give cost certainty for the client but there can be disadvantages later if variations are required, and there is disagreement about the rates to be charged for changes. A pricing document might be prepared during the tender stage, but it might not be detailed enough to capture all rates that could apply to changes. The drawings, specification and schedules should therefore capture as much detail as possible to minimise variations.
[edit] JCT contracts
The JCT Standard Building Contract is an example of a contract that can be used without quantitates. JCT give the following guidance for contracts ‘without quantities’:
- The project is generally not complex enough to require bills of quantities.
- The employer must provide drawings together with a description of works, and either a specification or work schedules at tender stage.
- The price and payment structure is based on a lump sum with monthly interim payments.
- Pre-construction services agreements can be used with this contract.
- This contract can be used with a framework agreement.
- This contract can be used for both private and public sector projects.
[edit] Related articles on Designing Buildings Wiki
- Approximate quantities.
- Bill of quantities.
- Contract documents.
- Form of contract.
- Lump Sum.
- Procurement route.
- Schedule of works.
- Tender documents.
- Tender pricing document.
- Types of bill of quantities.
- Unpriced bill.
[edit] External references:
Featured articles and news
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.