Without quantities
Contents |
[edit] Introduction
The term ‘without quantities’ refers to a construction contract or tender documents that do not include specific measured quantities of the items of work identified by the drawings and specifications. It can be used on projects where it is not possible to prepare a bill of quantities (BOQ) at the time of tendering. This might be because the design is progressed enough for tendering purposes but not firm enough to provide accurate quantities.
Smaller projects, or alteration work may also be tendered without quantities, for example where a schedule of works is prepared allowing the pricing of items, such as builders' work and fixing schedules. For more information see: Schedule of works.
An intermediate position between the two approaches is ‘approximate quantities’. For more information see: Approximate quantities.
[edit] Contract features
Tendering on the basis of “without quantities” can allow selection of the contractor and so expedite the project program. Generally, the design will be relatively complete, but may be insufficient time or information to determine the quantities. Drawings, specifications and schedules will generally form the key contract documents if projects are procured in this way.
Procuring ‘without quantities’ will result in a lump sum contract. There will be no re-measurement required and it can simplify the valuation process. This might initially give cost certainty for the client but there can be disadvantages later if variations are required, and there is disagreement about the rates to be charged for changes. A pricing document might be prepared during the tender stage, but it might not be detailed enough to capture all rates that could apply to changes. The drawings, specification and schedules should therefore capture as much detail as possible to minimise variations.
[edit] JCT contracts
The JCT Standard Building Contract is an example of a contract that can be used without quantitates. JCT give the following guidance for contracts ‘without quantities’:
- The project is generally not complex enough to require bills of quantities.
- The employer must provide drawings together with a description of works, and either a specification or work schedules at tender stage.
- The price and payment structure is based on a lump sum with monthly interim payments.
- Pre-construction services agreements can be used with this contract.
- This contract can be used with a framework agreement.
- This contract can be used for both private and public sector projects.
[edit] Related articles on Designing Buildings Wiki
- Approximate quantities.
- Bill of quantities.
- Contract documents.
- Form of contract.
- Lump Sum.
- Procurement route.
- Schedule of works.
- Tender documents.
- Tender pricing document.
- Types of bill of quantities.
- Unpriced bill.
[edit] External references:
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
















