Without quantities
Contents |
[edit] Introduction
The term ‘without quantities’ refers to a construction contract or tender documents that do not include specific measured quantities of the items of work identified by the drawings and specifications. It can be used on projects where it is not possible to prepare a bill of quantities (BOQ) at the time of tendering. This might be because the design is progressed enough for tendering purposes but not firm enough to provide accurate quantities.
Smaller projects, or alteration work may also be tendered without quantities, for example where a schedule of works is prepared allowing the pricing of items, such as builders' work and fixing schedules. For more information see: Schedule of works.
An intermediate position between the two approaches is ‘approximate quantities’. For more information see: Approximate quantities.
[edit] Contract features
Tendering on the basis of “without quantities” can allow selection of the contractor and so expedite the project program. Generally, the design will be relatively complete, but may be insufficient time or information to determine the quantities. Drawings, specifications and schedules will generally form the key contract documents if projects are procured in this way.
Procuring ‘without quantities’ will result in a lump sum contract. There will be no re-measurement required and it can simplify the valuation process. This might initially give cost certainty for the client but there can be disadvantages later if variations are required, and there is disagreement about the rates to be charged for changes. A pricing document might be prepared during the tender stage, but it might not be detailed enough to capture all rates that could apply to changes. The drawings, specification and schedules should therefore capture as much detail as possible to minimise variations.
[edit] JCT contracts
The JCT Standard Building Contract is an example of a contract that can be used without quantitates. JCT give the following guidance for contracts ‘without quantities’:
- The project is generally not complex enough to require bills of quantities.
- The employer must provide drawings together with a description of works, and either a specification or work schedules at tender stage.
- The price and payment structure is based on a lump sum with monthly interim payments.
- Pre-construction services agreements can be used with this contract.
- This contract can be used with a framework agreement.
- This contract can be used for both private and public sector projects.
[edit] Related articles on Designing Buildings Wiki
- Approximate quantities.
- Bill of quantities.
- Contract documents.
- Form of contract.
- Lump Sum.
- Procurement route.
- Schedule of works.
- Tender documents.
- Tender pricing document.
- Types of bill of quantities.
- Unpriced bill.
[edit] External references:
Featured articles and news
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.





















