Prolongation in construction contracts
As per the definition contained in the Society of Construction Law Delay and Disruption Protocol the term ‘prolongation’ refers to 'the extended duration of the works during which time-related costs are incurred as a result of a delay' - usually recognised as the additional projected time required to complete a contract extending beyond the contractual completion date.
Prolongation costs are the additional costs that a contractor has incurred as a result of the completion of the works being delayed by an event that is the responsibility of the other party (usually the Employer). Such events might include; failing to give the contractor possession of the site on the date specified in the contract; delays in giving instructions, and so on.
The contractor may incur additional costs as a result of having to remain on site for longer than anticipated, for example, additional labour costs, plant costs, off-site overheads, fluctuations, and so on.
Prolongation is sometimes described as being synonymous with ‘loss and expense’, however, this is incorrect. Loss and expense is a wider term that refers to matters which are the responsibility of the client that materially affect the progress of the works. This includes matters that disrupt, rather than delay the progress of the works, but still entitle the contractor to make a claim for additional costs incurred. Claims for disruption result from the additional cost of adopting inefficient working methods as a result of the disruption.
For more information, see Disruption claims in construction.
Prolongation and disruption therefore are two separate elements that might result in a claim for loss and expense. The prolongation element is dependent on the completion date being delayed.
Depending on the terms of the construction contract, prolongation might relate to the project as a whole, or to a specific aspect of it.
Generally a disruption event is easier to prove than a critical delay prolongation event i.e. a failed critical delay prolongation claim will often be used as proof of disruption. However, prolongation costs are often considered easier to demonstrate than disruption costs.
For more information see: Loss and expense.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.
Construction Management, 10 June.
Heat pumps beat boilers in new home tests.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
















