Prolongation in construction contracts
As per the definition contained in the Society of Construction Law Delay and Disruption Protocol the term ‘prolongation’ refers to 'the extended duration of the works during which time-related costs are incurred as a result of a delay' - usually recognised as the additional projected time required to complete a contract extending beyond the contractual completion date.
Prolongation costs are the additional costs that a contractor has incurred as a result of the completion of the works being delayed by an event that is the responsibility of the other party (usually the Employer). Such events might include; failing to give the contractor possession of the site on the date specified in the contract; delays in giving instructions, and so on.
The contractor may incur additional costs as a result of having to remain on site for longer than anticipated, for example, additional labour costs, plant costs, off-site overheads, fluctuations, and so on.
Prolongation is sometimes described as being synonymous with ‘loss and expense’, however, this is incorrect. Loss and expense is a wider term that refers to matters which are the responsibility of the client that materially affect the progress of the works. This includes matters that disrupt, rather than delay the progress of the works, but still entitle the contractor to make a claim for additional costs incurred. Claims for disruption result from the additional cost of adopting inefficient working methods as a result of the disruption.
For more information, see Disruption claims in construction.
Prolongation and disruption therefore are two separate elements that might result in a claim for loss and expense. The prolongation element is dependent on the completion date being delayed.
Depending on the terms of the construction contract, prolongation might relate to the project as a whole, or to a specific aspect of it.
Generally a disruption event is easier to prove than a critical delay prolongation event i.e. a failed critical delay prolongation claim will often be used as proof of disruption. However, prolongation costs are often considered easier to demonstrate than disruption costs.
For more information see: Loss and expense.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.