Constructive acceleration
This concept is not (currently) a recognised concept under English law.
Constructive acceleration is acceleration of the construction works following failure by the employer to recognise that the contractor has encountered employer delay for which the contractor is entitled to an extension of time and which failure required the contractor to accelerate its progress in order to complete the works by the contract completion date.
This situation may be brought about by the employer’s denial of a valid request for an extension of time or by the employer’s late granting of an extension of time.
For more information see: https://www.scl.org.uk/resources/delay-disruption-protocol
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Why being a mentor can help your career.
Channel 4 broadcaster to host 125th anniversary ceremony.
Listed structures on the rail network
Heritage interests and operational requirements must be balanced.
Historic England publishes research into embodied carbon when retrofitting traditional buildings.
New Prime Minister delivers on ECA call for cut in electricity costs.
CIOB reacts to the announcement of Andy Burnham as Prime Minister.
Heritage and conservation science workforce survey - Have your say.
England's Suburbs 1820-2020. Book review.
New, more proportionate and targeted approach for higher-risk building assessments.
Government brings British Steel into public ownership.
UKCW Birmingham returns with bold new theme and focus.
New guidance published on competence requirements for self-certification schemes.