Time management of construction projects
See also: Scheduling construction activities.
Time management is the process of organising and implementing a strategy related to the time required for work activities on a project. Effective time management is essential to successfully and efficiently meeting budget and programme targets, as well as achieving profitability.
Projects can risk incurring unnecessary costs and delays as a result of ineffective time management, either by failing to allow for the full complexity of a project, or by failing to effectively manage scheduled work or unexpected events.
On large projects, the client may appoint a programme consultant to prepare a detailed programme for the project including an outline programme for construction if a contractor has not been appointed. Once the contractor is appointed, they will take responsibility for programming the construction works, but the programme consultant may continue to develop an overall programme for the client.
During the planning stage, all work activities should be properly understood, and planned in detail to optimise the allocation of resources and reduce the potential for ‘unknowns’. Estimates can then be made of how long each activity will take. This is critical to the setting of milestones and deadlines, for allocation of resources, and for determining the pricing of contracts and cashflow requirements.
As well as work packages, time management should also make allowance for activities including:
- The interrelationships between tasks.
- Project management administration.
- Liaison with third parties, such as the local authority.
- Client approvals and decision making processes.
- Training.
- Accidents and emergencies.
- Internal and external meetings.
- Holidays and sickness in staff.
- Suppliers and subcontractor activities.
- Equipment breakdowns.
- Missed deliveries by suppliers.
- Interruptions to work progress due to inclement weather.
- Inspections, testing and other forms of quality control.
The concept of 'float' describes the time that an activity can be delayed without changing the overall project duration. The float is obtained by subtracting the duration of activities from the available time. The critical path is determined by all activities were the total float is zero.
The critical activities have to be carried out without delay, any modification in their duration results in change in the project’s duration. The duration of an activity can sometimes be reduced by adding additional resources, but this will also increase its cost.
There are a wide range of articles on Designing Buildings Wiki describing a range of tools, devices and techniques that can be used to assist with time management.
- Acceleration.
- Contractor's master programme.
- Critical path analysis.
- Earned value.
- Fast-track construction.
- Gantt chart.
- Information release schedules.
- Key performance indicators.
- Line of balance (LOB).
- Milestones or gateways.
- Pareto analysis.
- Precedence diagram method.
- Programme for building design and construction.
- Project crashing.
- Resource leveling.
- Schedule performance index (SPI).
- Short period programme.
- Time-location chart.
For more information see: Scheduling construction activities, and Programme for building design and construction.
[edit] Related articles on Designing Buildings Wiki
- Acceleration of construction works.
- Activity schedule.
- Construction management.
- Contractor’s master programme.
- Contractor's working schedule.
- Construction project.
- Gantt chart.
- How to manage construction plant.
- Key performance indicators.
- Line of balance (LOB).
- Milestones.
- Programme for building design and construction.
- Progress of construction works.
- Project benchmarking.
- Project manager.
- Resource leveling.
- Resource management.
- Scheduling construction activities.
- Schedule performance index (SPI).
- Time-location chart.
- Time management.
- Transition time.
[edit] External references
Featured articles and news
Tackle the decline in Welsh electrical apprenticeships
ECA calls on political parties 100 days to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.























