Design web for building design
No matter how big or small a project, knowing where you are in the design process and identifying where problems lie is absolutely fundamental to achieving a successful outcome, and in that, monitoring the design is crucial.
However, whilst designers may be asked to take on lead consultant or lead designer roles, many practices do not have in house management support. As a consequence, they may seek to improve the way their projects are managed, either by developing tools and techniques internally or by outsourcing this requirement to other, more suitable consultants.
This is not straight-forward, as design is not predictable, nor is it as sequential as the construction process. The construction process is typically scheduled using tools such as Gantt charts, where tasks are linked to show sequences of activities, dependencies and critical paths.
However, it can be argued that design is an activity-related as opposed to time-related process, and that the days have passed where architecture, structure and services designers worked independently and measuring design progress was simply a matter of counting drawings.
Designers also tend to b every visual individuals. Having to decipher a bar chart to determine design progress may not be something that comes naturally. This makes it a challenge to schedule and monitor design team activities and progress accurately and meaningfully.
The ‘Design Web’ provides an alternative method of monitoring and reporting on design activity and progress. Using fairly simple techniques, it is a very visual tool that allows designers to take a snapshot of the entire project at any time in the project life cycle. It is something that is used to ensure that all the pieces of the design jigsaw are being progressed and if not, instantly see where the problems or blockages lie.
This is also useful for showing progress to clients.
The ‘Design Web’ captures the design tasks necessary in any given period, weighted and presented in a simple graphical form that can be easily understood by all. They are used by design teams to assess progress and subsequently target effort and resources into the right areas, allowing them to produce a fully integrated and coordinated design. It enables everyone to clearly see where problems lie and where the team is progressing well.
Work begins in the centre of the web, and progress then ‘grows’ from the centre towards the outer edge that represents 100% completion.
There will always be a need to plot the design stages and key milestones in a linear way in a bar chart form (using a Gannt chart) as this provides a sequential plan showing how to progress through the project. However, just plotting design onto a Gannt chart and then drawing a line down it to reflect current progress does not accurately or usefully represent the real situation. Gannt charts are useful for plotting key milestone dates, key decision dates critical paths and so on, but not are not the only or the best tool for gauging design progress.
[edit] Related articles
Featured articles and news
ECA, JIB and JTL back Fabian Society call to invest in skills for a stronger built environment workforce.
Women's Contributions to the Built Environment.
Calls for the delayed Circular Economy Strategy
Over 50 leading businesses, trade associations and professional bodies, including CIAT, and UKGBC sign open letter.
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.