Culpable delay in construction contracts
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. This is described as an extension of time (EOT). The contractor may (but is not necessarily) also be entitled to claim for loss and expense associated with the delay.
Culpable delay (sometimes referred to as 'contractor delay') on the other hand is a delay that is entirely the fault of the contractor. Where the contractor is culpable for a delay, they have no entitlement to an extension of time or loss and expense.
Where there is a culpable delay, the period of time after the contractual date for completion has passed is referred to as the period of contractor culpable delay, and during this period, the contractor will be liable to pay liquidated and ascertained damages (LAD's) to the client.
Concurrent delay refers to the complex situation where more than one event occurs at the same time, but where not all of those events enable the contractor to claim an extension of time. For more information, see Concurrent delay.
In Carillion Construction Ltd. v Woods Bagot Europe Ltd. and others [2016], the Technology and Construction Court (TCC) held that a subcontractor who had caused a delay, was also entitled to an extension of time and that this should run contiguously from the contractual completion date. This meant that the subcontractor’s period of culpable delay was extinguished, and they were no longer liable for their own delay.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.
Why construction can't afford to ignore the skills gap.
Building Safety Regulator, 19 August
Gill Kernick appointed Independent Chair of Residents’ Panel.
Connecting knowledge, technology and conservation
Building competence for the future of built heritage.

















