Common refusals of extensions of time
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. This is described as an extension of time (EOT).
When it becomes reasonably apparent that there is, or that there is likely to be, a delay that could merit an extension of time, the contractor should give written notice to the contract administrator identifying the relevant event that has caused the delay. If the contract administrator accepts that the delay was caused by a relevant event, then they may grant an extension of time and the completion date is adjusted.
Common reasons for the refusal of an application for extensions of time include:
- Where the contractor has underperformed, for example, as a result of insufficient workforce or failure to obtain plant, goods or service.
- When there has been poor, but not exceptionally adverse weather.
- When the evidence or other information presented to demonstrate that the contractor has suffered irrecoverable delays is insufficient.
- If an extension of time has already been given for that event.
- Where more than one event occurs at the same time. See Concurrent delay for more information.
- The event cited does not constitute a relevant event.
- An event does not constitute force majeure.
- An event does not constitute a specified peril.
- The contractor has not taken steps to mitigate the delay
[edit] Related articles on Designing Buildings Wiki
- Acceleration of construction works.
- Change order.
- Compensation event.
- Contract administrator.
- Contract claims.
- Culpable delay.
- Delay damages.
- Extension of time.
- Extension of time - approval letter example.
- How to prepare a claim for an extension of time.
- Practical completion.
- Project programme.
- Time certainty.
- Time extension.
- Time Risk Allowance TRA.
- Variations.
Featured articles and news
Report on the construction sector in Ireland
TASC/CIOB study looks at post-pandemic struggles and trends.
Revised targets for Carbon Budget 6
The Government announces recalibrated goals.
ECA proposes strategies for the present and the future.
Paul Morrell to lead independent review of the construction products testing regime.
Standard will help employers foster wellbeing and manage psychosocial risks.
The United Nations has approved the IFSS common principles
Global fire standards for safety of people and property.
An introduction to the 5 core principles of lean.
Civil engineers and environmental methods of construction
Can the profession use its skills to save the world from climate change?
How faulty science resulted in sanitation reform.
Conserving the Hilda Besse Building
Improving facilities, accessibility and overall appearance.
BSRIA IAQ topic guide published
Free download of TG 12/2021 available.
Electrotechincal mentors wanted
TESP works with The Youth Group to form skill sharing network.
OpenBuilt supply chain technology in development
Big tech collaborates on platform for the built environment.
Concerns raised over Future Buildings Standard
Letter signed by 21 organisations sent to MHCLG.
Receive the Designing Buildings newsletter
Click the button to subscribe.