Groundworks on construction projects
Contents |
[edit] Introduction
The term ‘groundworks’ refers to work done to prepare sub-surfaces for the start of construction work. Aside from any demolition or site enabling works that may need to be carried out, groundworks are usually the first stage of a construction project and may include:
- Ground investigation.
- Site clearance.
- Substructure and ground stabilisation works.
- Site services.
- Landscaping.
[edit] Ground investigation
As a matter of good practice and a legal requirement of most local authorities, a ground investigation of the site is generally carried out to help identify past land uses, stability and potential problems. These investigations allow data to be accumulated and used for effective design, as well as allowing any potential defects or issues, such as contamination or abandoned mine workings, to be considered.
An assessment of ground conditions typically includes geology, hydrology, hydrogeology, soil conditions and contaminated land issues.
See: Ground conditions for more information.
[edit] Site clearance
As part of the initial preparatory works, the site will generally need to be cleared and the topsoil taken up from the footprint of the structure. The depth will depend on the lay of the land, and if it is a sloping site then the ground may need to be levelled. If required, retaining walls may be constructed in order to create level development platforms.
[edit] Substructure and ground stabilisation
Substructure is defined by the RICS as ‘All work below underside of screed or, where no screed exists, to underside of lowest floor finishes including damp-proof membrane, together with relevant excavations and foundations (includes walls to basements designed as retaining walls).’
Retaining walls can be made from stone, brick or blockwork, reinforced concrete or timber. Basement excavations commonly use sheet piling which is a relatively cheap method of retaining wall construction. This involves the use of a large scale hydraulic jack hammer to drive steel sheet piles into the ground and interlocked, forming a continuous wall.
Other methods of ground stabilisation include:
[edit] Soil nails
Holes drilled and steel bars inserted into the slope face which are then grouted in place. Mesh is attached to the bar ends to hold the slope face in place.
For more information, see Soil nailing.
[edit] Ground anchors
Steel cables with metal wedges on their ends. The metal wedge end is driven pneumatically into the slope face to the desired depth, the cable pulled taut and attached to a finishing plate to maintain tension.
[edit] Geosynthetic materials
These can be incorporated into retaining walls and embankments and provide reinforcement. Geotextiles are woven and allow the passage of ground water through them. Geomembranes are impermeable and are typically used as liner materials. Geocomposites combine both materials.
Foundations provide support for structures, transferring their load to layers of soil or rock that have sufficient bearing capacity and suitable settlement characteristics. There are a very wide range of foundation types suitable for different applications, depending on considerations such as:
- The nature of the load requiring support.
- Ground conditions.
- The presence of water.
- Accessibility.
- Sensitivity to noise and vibration.
Very broadly, foundations can be categorised as shallow foundations or deep foundations. Shallow foundations are typically used where the loads imposed by a structure are low relative to the bearing capacity of the surface soils.
Deep foundations are necessary where the bearing capacity of the surface soils is not adequate to support the loads imposed by a structure and so those loads need to be transferred to deeper layers with higher bearing capacity.
See: Foundations for more information.
[edit] Services
Site services may include temporary and permanent drainage and other utilities connections. Complex sites may require specialist tunnelling or shaft sinking solutions to enable service ducts and cabling to the installed. Existing services such as water and electricity cables may also need to be altered.
[edit] Landscape
Landscaping may include earthworks to remodel the site and hard landscape such as ‘black top’ surfacing of roads and car parks.
See: Landscape design for more information.
[edit] NBS categorisation
NBS categorise groundworks as:
| D20 | Excavating and filling |
| D21 | Ground gas collection and venting systems |
| D30 | Piling |
| D40 | Embedded retaining walls |
| D41 | Crib walls, gabions and other gravity retaining walls |
| D45 | Soil nailing |
| D50 | Underpinning |
[edit] Related articles on Designing Buildings Wiki
- Backfilling.
- Building foundations.
- Continuous flight auger piles.
- Diaphragm wall.
- Driven piles.
- Excavation.
- External works.
- Footings.
- Ground conditions.
- Ground heave.
- Ground improvement techniques.
- How deep should foundations be?
- Micropiles.
- Pad foundation.
- Pile foundations.
- Raft foundation.
- Retaining walls.
- Screw pile foundations.
- Settlement.
- Sheet piles.
- Subsidence.
- Substructure.
- Temporary works.
- Trench.
- Trial pit.
- Underpinning.
- Underreaming.
[edit] External references
- Homebuilding - What will it cost getting out of the ground?
- The Construction Centre – Groundwork and substructure
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings for people to come home to... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”

























