Backfilling
Contents |
[edit] Introduction
Backfilling is the process of reusing or replacing the soil that is removed during the excavation of foundations, ground bearing slabs or other groundworks to support and strengthen a structure. It protects foundations and forms part of the substructure of slabs, roadways, walkways and other groundwork elements.
Backfill can be made up of the same soil that was removed during excavation, or can be a mixture of imported soil, rocks and stones depending on the structural requirements. The need for backfilling will be established during ground investigations which will also be used by the engineers to formulate a design. Backfill is quantified in m3.
[edit] Backfill with excavated material
During the excavation process, excavated soil is set aside for later use. Once foundations or other concrete works are complete the previously set aside soil is used to backfill the foundation or other structural areas. Excess soil might be taken away from site or set aside for use in other parts of the project at a later stage. When excavated material is set aside for later use it should be protected from the elements. Excavated material should be stockpiled according to class or type of material.
The site parameters, soil type and design will dictate whether backfill with excavated materials is possible. For example, some sites might be so confined that stockpiling is not be a viable option.
[edit] Backfill with imported soil
The structural requirements for each project and situation will be unique and it might be necessary to use strengthened material for backfilling. The site constraints might also be a factor in the requirement to use imported soil.
[edit] Grading backfill
Backfill materials can generally be graded as:
- Coarse grained soils – gravelly and sandy soils ranging from clay to gravel.
- Fine grained soils of low to medium plasticity – inorganic clays of low to medium plasticity, inorganic silts and very fine sands of low plasticity.
- Rock – suitability depending on hardness and gradation. Hard rock might be specified for crushing.
- Shale – rock like material that breaks down under compaction.
- Marginal materials - including fine-grained soils of high plasticity and expansive clays.
- Commercial by-products - furnace slag or fly ash.
Backfill material should be homogeneous, consistent with required characteristics and free of organic matter and pockets. An engineer should visit the site to ensure that only the suitable backfill material is used.
[edit] Method for backfilling
Each project will have a unique specified method for backfilling. This will be established by the engineers of the project and described in the relevant specifications and drawings. There will be different methodologies for each element of groundworks in the project; the backfill requirements for supporting ground bearing slabs will be different to the backfill requirements for trenches.
In general, backfilling will be done in layers after the excavated areas are compacted and cleared of debris. Elements of working in confined spaces should be taken into consideration during the planning process to establish the methodology of backfilling required.
[edit] Related articles on Designing Buildings Wiki
- Building foundations.
- Confined spaces.
- Excavating plant.
- Ground improvement techniques.
- Groundworks.
- Mass haul movement.
- Over excavation.
- Ripping.
- Road construction.
- Substructure.
- Surplus excavated material.
- Temporary works.
- Trench support.
- Trial pit.
- Types of soil.
- Underground.
[edit] External references
Featured articles and news
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”




















