Trench support
Contents |
[edit] Introduction
A trench is defined as an excavation when its length greatly exceeds its depth. Shallow trenches are usually considered to be less than 6 m deep and deep trenches greater than 6 m. Depending on the dimensions of a trench, excavation can either be carried out by hand or using a mechanical digger. Trenches are commonly required to allow services, pipelines or foundations to be laid.
Water ingress into the trench is often a major issue and ground water table locations and soil strata should be investigated before any extensive excavation takes place.
Over short periods of time for relatively shallow depths most soil types will stand almost vertically without any problems. However, trenches other than those which are relatively shallow may require a trench support scheme.
[edit] Timber supports
Historically, trenching involved using timber to support horizontal and vertical soil loads and this technique is still used today. Timber trenching is generally used for low risk, narrow trenches, shafts or headings. The timber solutions require good workmanship and are reasonably labour-intensive, however they are versatile and the equipment required is easy to handle and transport.
[edit] Trench boxes
Trench boxes are suitable for low-risk situations in stable, dry ground and can be placed in pre-excavated trenches or installed using the ‘dig and push’ technique. The system requires at least two struts at each panel for stability which must be considered when access is required for construction work or piping.
For more information, see Trench box.
[edit] Trench sheets
Trench sheets are the most adaptable of the systems available, and are most commonly used to retain poorer soil. They can support deeper trenches with larger surcharges and provide a continuous support. They require multiple levels of strut support and the slenderness of the sheets can often limit the depth of the trench as they are installed by light machinery and could buckle under large vertical loads.
[edit] Related articles on Designing Buildings Wiki
- Backfilling.
- CDM.
- Crane supports.
- Demolition.
- Excavation.
- Facade retention.
- Falsework.
- Formwork.
- Health and Safety.
- Scaffolding.
- Shoring.
- Temporary works.
- Trench box.
- Trenching equipment.
- Tunnelling.
[edit] External references
- BS5975:2008 + A1: 2001 Code of Practice for Temporary Works Procedures and the Permissible Stress Design of Falsework (BSI 2011).
Featured articles and news
Conserving the Hilda Besse Building
Improving facilities, accessibility and overall appearance.
BSRIA IAQ topic guide published
Free download of TG 12/2021 available.
Electrotechincal mentors wanted
TESP works with The Youth Group to form skill sharing network.
OpenBuilt supply chain technology in development
Big tech collaborates on platform for the built environment.
Concerns raised over Future Buildings Standard
Letter signed by 21 organisations sent to MHCLG.
The infrastructure planning process
A look at the Government's strategic approach.
Steps to help reduce the spread of infection inside buildings.
Urban exploration and construction
This social media-centred hobby can be both dangerous and illegal.
Millwork wall treatment with a long and illustrious history.
Weekly workplace noise estimator tool
HSE introduces cumulative exposure calculator.
The Edwardians and their houses.
Cut off from civilian life for over 900 years.
Can net zero and levelling-up align?
Gaining green support from the carbon giants.
Receive the Designing Buildings newsletter
Click the button to subscribe.