Cofferdam
Contents |
[edit] Introduction
Cofferdams are temporary structures used where construction is being carried out in areas submerged in water. They are most commonly used to facilitate the construction or repair of dams, piers and bridges. The aim of a cofferdam is to be as watertight as possible to create a dry area in which to complete the required building works, or at least to limit water ingress to a safe level that can be pumped away.
Cofferdams must be able to withstand very high pressures and can create a hazardous situation if they are installed incorrectly. They are usually constructed using steel sheet piles driven into the ground and supported by internal braces and cross braces. Timber sheet piles, concrete or a combination of materials can also be used.
A cofferdam can be any shape. Its design will be depend on the depth required, the required working area, soil conditions, fluctuations in the water level, and so on.
[edit] Types of cofferdam
There are several different types of cofferdam. The most common are as follows:
[edit] Typical piled cofferdam
The construction sequence for a typical piled cofferdam is as follows:
- Pre-dredge the proposed area of the cofferdam.
- Drive temporary support piles into place.
- Install bracing frames to support piles.
- Drive sheet piles into place.
- Pump out water from the inside of the cofferdam.
- Progressively install internal bracing as required.
- Excavate ditch to allow leakage to run to one place.
- Place rock fill as a leveling and support course.
[edit] Earthen
This is a simple form of cofferdam suitable for areas of shallow water with low current velocity, where a sloped earthen embankment is built up around the area to be enclosed. The bank should be a combination of clay and sand or clay and gravel.
[edit] Rock-fill
If the water to be retained is not shallow enough for an earthen cofferdam, stone or rubble can be used instead. The stones are built up in the required shape of the cofferdam, and voids filled with earth, gravel or stone-chips.
[edit] Single-walled
This type of cofferdam is most suitable when the area to be enclosed is particularly small and the water is of a deeper level, roughly 4-6 m. Guide piles made of timber are driven into the ground and bracing constructed before sheet piles are driven into place and secured to the bracing using bolts.
[edit] Double-walled
Single-walled cofferdams become unfeasible as larger areas are required in deeper water, and so double-walled cofferdams are sometimes necessary. Two walls are built with a gap between them, the thickness of which is dependent upon the depth of water.
The general rule is for the thickness of the wall to equal the depth of water up to 3 m, greater depths require 3 m plus half the excess depth. The two wall faces are connected at the top using steel rods placed at close intervals.
[edit] Crib
This is commonly used in deep waters where the ground is particularly hard. The sheet piles are supported by a horizontal framework of timbers, known as cribs, which form pockets to be filled with earth or stones. This is constructed on land prior to being moved into position in the water. The crib is sunk into position, the internal space filled with stone or other material and timber or steel piles are then driven around the boundary of the crib.
[edit] Cellular
This type of cofferdam is most suitable for deep water areas, most commonly for during marine construction such as dams and wharves. Straight web steel sheet piles are driven into the ground to form a series of inter-connected cells of specific shapes which are filled with clay, sand or gravel to enable the structure to withstand the lateral forces of the water pressure. There are two common shapes:
- Circular type: Each cell acts as a self-supporting independent unit so each cell can be completely filled before construction of the next cell begins.
- Diaphragm type: Made from interconnected steel sheet piles using circular arcs at the inner and outer sides. The cells are then filled with coarse-grained soils, all at the same rate to avoid rupturing.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Bridge construction.
- Caisson.
- Coastal defences.
- Difference between cofferdams and caissons.
- Driven piles.
- Formwork.
- Geothermal pile foundations.
- Groundwater control in urban areas.
- Grouting in civil engineering.
- Micropiles.
- Pile foundations.
- Pumps and dewatering equipment.
- Retaining walls.
- River engineering.
- Screw piles.
- Sheet piles.
- Shoring.
- Temporary works.
- Trench box.
- Underpinning.
- Underwater foundations.
- Watercourse.
- Water engineering.
[edit] External references
- Deep excavation - Cofferdams
- The Construction Civil - Types of cofferdam
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.