Curtain wall systems
Curtain wall systems are non-structural cladding systems for the external walls of buildings. They are generally associated with large, multi-storey buildings.
Curtain walls separate the interior from the exterior, but only support their own weight and the loads imposed on them (such as wind loads, seismic loads, and so on) which they transfer back to the primary structure of the building. This is in contrast to many forms of traditional construction in which the external walls are a fundamental part of the primary structure of the building.
Typically curtain wall systems comprise a lightweight aluminium frame onto which glazed or opaque infill panels can be fixed. These infill panels are often described as 'glazing' whether or not they are made of glass.
Curtain wall systems emerged in the 19th century with the development of large glass panels and became more common from the 1930's when aluminium was made available as a construction material for the first time.
They are now closely associated with the modernist movement and in particular, the International style, which became popular in the middle of the 20th century. This was an ornament-free, stark form of modernism, characterised by the repetition of units and the extensive use of glass. It is a style that is still in widespread use for tall buildings in cities around the world.
Curtain wall systems can be custom designed and manufactured, but are often manufacturer's proprietary systems that can be bought 'off the shelf'. Custom-designed systems are generally only cost effective for larger buildings.
Curtain walls can adopt a 'stick' system, or can be unitised:
- Stick systems are installed piece by piece on site, with the glazing inserted into the frame from the inside or the outside depending on access conditions.
- Unitised systems are pre-fabricated in modules off-site and delivered in panels. Unitised systems are better able to exploit the benefits of factory condition manufacturing and quality control and require lower installation time on site.
There are a wide range of possible infill panels for curtain wall systems, including:
- Vision glass (which may be double or triple glazed, may include low-e coatings, reflective coatings and so on).
- Spandrel (non-vision) glass.
- Aluminium or other metals.
- Stone or brick veneer.
- Terracotta.
- Fibre-reinforced plastic (FRP).
- Louvres or vents.
Panels are often composites, with the facing materials bonded to, or 'sandwiching' an insulated core such as polyethylene (PE) or polyurethane (PUR), a profiled metal core or a mineral core. See Metal composite panels for more information.
Frame and panel designs are very complex, as they need to perform multiple functions:
- Transferring loads back to the primary structure of the building.
- Providing thermal insulation and avoiding cold bridging and condensation.
- Providing fire, smoke and acoustic separation. This is particularly difficult at joints between the curtain wall system and interior walls and floors.
- Creating a barrier to water penetration.
- Accommodating differential movement and deflection.
- Preventing panels from falling out of the frame.
- Allowing for opening windows.
- Preventing the accumulation of dirt.
On tall buildings, access systems must be provided to allow regular inspection, maintenance, cleaning and replacement (in particular, replacement of external seals).
Systems used to prevent the passage of water through joints (driven by pressure differences between the inside and outside) include; face-sealed, water-managed and pressure-equalised (PE or 'rainscreen') systems.
Pressure-equalised systems create a rebate between the internal and external gasket that is ventilated to the outside so that there is no pressure difference between the outside and the rebate. As a result, water is not driven into the rebate by a pressure difference that would otherwise build up across the outer gasket. Any rain that penetrates the outer seal can be drained to the outside through the vents, or weep holes. This is considered to be more reliable than face-sealed systems that attempt to create a 'perfect' seal which inevitably fails due to pressure-driven moisture.
Water-managed systems are similar to pressure-equalised systems, but there is no attempt to prevent water penetrating the outer seal, and so the primary function of weep holes or drains is to drain water rather than to allow pressure equalisation.
See Rainscreen for more information.
There is very good technical information about the design of curtain wall systems on the Whole Building Design Guide website (USA National Institute of Buildings Sciences), including typical details.
[edit] Related articles on Designing Buildings
- Brick veneer.
- British post-war mass housing.
- Building fabric.
- Cladding.
- Composites.
- Facade cleaning.
- Fire performance of external thermal insulation for walls of multistorey buildings, third edition (BR 135).
- Framed-type glass curtain wall.
- Glass mullion system.
- Grenfell Tower.
- Metal composite panels.
- Off-site prefabrication of buildings: A guide to connection choices.
- Patent glazing.
- Rainscreen.
- Sandwich panel.
- Structural glass assembly.
- Structural Insulated Panels.
[edit] External references
Featured articles and news
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.
A brief run down of changes intentions from April in an onwards.























Comments