Shell and core
Contents |
[edit] Introduction
The concept of shell and core (or base build) is that the developer's scope of works is the design and construction of the base building. A range of other construction and fit out works are left to be completed before the building is occupied.
The concept originated in the USA where it was applied to office buildings built by developers for rent. American developers initially fitted out offices, installing access floors, carpet tiles, ceilings, air conditioning and lighting on the basis of a notional layout for prospective tenants. However, the actual tenant's ideas often differed from the developer’s notional layouts and so money was wasted taking down ceilings and taking up floors, while mechanical and electrical services had to be altered to accommodate partition layouts.
It then became common practice for developers to purchase the materials for the fit out of tenant areas, but not to install them, leaving them stacked on the open area floors.
Rosehaugh/Stanhope introduced a similar idea in the UK in its ground-breaking Broadgate development in the City of London. Broadgate office buildings were specifically designed for the financial markets following deregulation. Rosehaugh/Stanhope did not supply ceiling tiles, carpet tiles etc, but allocated its tenants a rent-free period and an allowance for the landlord's notional fitting out. This became known in lease arrangements as a category A fit out allowance.
Following the lead of Broadgate in the eighties, agents in the chartered surveying world accepted that rents were not affected by the principles of shell and core and it became widespread in the office commercial market.
For more information, see Advantages of shell and core.
[edit] Scope
The agreement to lease between landlord and tenant should clearly define:
- What comprises the shell and core built by the developer, including space provision in common areas for tenant equipment such as standby generators, extra chillers, or uninterrupted power supply plant.
- What constitutes category A fit out installed by the tenant but funded by the developer/landlord.
- What tenant equipment is to be installed in common areas.
[edit] Normal shell and core provision for a high-spec city office
Shell and core will typically comprise the structure, its cladding, its base plant, completed common areas and external works. More specifically it will generally include:
- Roads, paths, pavements, external lighting, security systems, fencing and boundary walls, drainage systems, incoming services, hard and soft landscaping, signage and all statutory requirements relevant to the site.
- Foundations and fire clad structure with column grid and clear structural floor heights defined.
- Building envelope, including insulation, external walls, glazing, balustrade and roofs.
- Completely finished circulation and common areas including main reception, lobbies, staircases, toilets, plant rooms, riser shafts, lift shafts, basements, loading bays and car parking. Fire compartmentation should also be part of the shell and core provision.
- All base plant, mechanical and electrical systems to plant rooms and services in shafts with air capped off by a fire damper to each tenant leased zone, electrical services connected to tenant’s zone switch panels and water and sprinkler services taken to each tenancy where they are capped off. Base plant will generally include :
- High and low voltage switchgear.
- Transformers.
- Lift systems.
- A standby generator.
- Boilers.
- Chillers.
- Cooling towers.
- Water and fuel tanks.
- Sprinkler plant.
- Building control systems.
- Air conditioning chambers and fans.
- Water and fuel pumps.
- Dry risers.
- Fire detection, alarm and hose reel systems.
See Fit out for a description of the different categories of fit out.
[edit] Programme
It is not unusual for a tenant to start fitting out their demised areas prior to the completion of the landlord shell and core works, although the rent-free period (to allow the tenant to fit out category A works) will be triggered by practical completion of the shell and core works.
Practical completion of the shell and core works should be defined by certification by the landlord’s contract administrator and will include all requirements under the building regulations for occupation other than those that await completion of tenant's work.
Because of the complexity of commissioning landlord and tenant's work contemporaneously, it is advisable that the setting to work of service systems and commissioning activities are carried out by an independent commissioning agency with a duty of care to both landlord and tenant.
[edit] Related articles on Designing Buildings
- Advantages of shell and core.
- Base construction.
- Building regulations.
- Client commissioning.
- Commissioning v testing.
- Commissioning.
- Equipment.
- Fit out.
- Furniture fixtures and equipment.
- Multi-storey structure.
- Practical completion.
- Rent free period.
- Set to work.
- Shear wall.
- Skeleton frame.
- Structural systems for offices.
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Planning condition discharge in England and Wales
A brief exoplanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.





















Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.