Furniture fixtures and equipment FF&E
FF&E refers to the procurement of furniture, fixtures and equipment.
This might be procured separately to the main construction contract (or elements of them), particularly by clients that already have systems in place for procuring fixed and loose furniture, fittings and equipment; for example schools, universities, or hospitals.
It is very important under such circumstances to define very clearly which contract every element of FF&E is within (for example, there may still be unusual or large items that it may be more sensible to procure under the main contract).
It is also important to ensure that any building work required for the installation of such items is identified and procured, that any services required (such as power or drainage) are identified and that the installation of FF&E is properly integrated into the main contract.
Requirements that affect the main contract might include:
- Built-in equipment requiring mechanical or electrical connections, such as fume cupboards or drinks stations. A description of built-in equipment should include; location, size, and requirements for power, air, water, drainage and telecommunications connection.
- Built-in equipment that does not require services such as cupboards or shelving. These should be described in terms of their location and size.
- Stand-alone loose furniture and equipment requiring services, such as washing machines, coffee machines and scanning equipment in hospitals. These should be described in terms of their location, size, and requirements for power, air, water, drainage and telecommunications connection.
- Stand-alone loose furniture and equipment not requiring services such as tables and chairs. These should be described in terms of their location and size.
It is also important that any elements that are outside of the main contract are included in the client's cost plans.
FF&E can be procured from specialist suppliers, or suppliers with whom the client already has a long term relationship. This may include maintenance arrangements. Some elements may be specially designed by FF&E designers or sourced by FF&E consultants. There is also a need for a carefully managed FF&E inventory and logistical planning to ensure items are available on-site at the right time.
In managing the procurement of FF&E, consultants take on the complicated and time-consuming task of coordinating with the design team, external vendors and internal departments for the following:
- Programming and planning.
- Sourcing.
- Project procurement strategy and risk analysis.
- Request for proposal (RFP) document development.
- RFP process management.
- Contract negotiation and buy-out.
- Order expediting and tracking.
- Installation, product acceptance and close-out.
For more information, see FF&E consultant.
[edit] Related articles in Designing Buildings
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.