Scope of services
The term ‘appointment’ generally describes the process in which the client contracts designers or other consultants to perform expert tasks on a project. With all forms of appointment it is important that there is clarity about the scope of services being provided, particularly where a range of consultants is being appointed. There might otherwise be uncertainty about which consultant is responsible for which aspects of the project, what fee is chargeable, what services are within the agreed fee and what services might be considered ‘extras’.
For this reason, appointment agreements often include, or refer to a ‘scope of services’ or ‘schedule of services’. A scope of services sets out precisely what services a consultant will be performing on a project. Scopes of services may also be prepared for contractors where they are carrying out design work, or for consultants appointed by contractors on design and build projects.
A scope of services may be a bespoke document, drafted for a particular project, or may be prepared based on standard pro-forma documents available from organisations such as the Royal Institute of British Architects, the Royal Institute of Chartered Surveyors, the Construction Industry Council and the Association for Consultancy and Engineering.
A scope of services may:
- List the fullest range of services that may be provided, and then items are struck through if they are not being provided within the fee.
- Offer a tick box system to indicate whether services are being provided or not.
- Include a list specifically setting out services that will not be provided.
- Provide options, such as; to ‘carry out’ services or to ‘organise’ them; to provide cost consultancy services or not and so on.
- Indicate the basis on which the services will be charged, for example, ‘T’ indicating time-based, or ‘LS’ indicating a lump sum fee.
If a design responsibility matrix is being prepared, then this should be aligned with the scope of services for the consultants involved in the project. There are a number of software systems available that can automate this process.
Areas where it is particularly important to be certain who is providing services include:
- Interior design and artwork.
- Landscape design.
- Highways, fencing and gates.
- Acoustics.
- Vibration control.
- Below and above ground drainage.
- Fire protection and safety systems.
- Lightning protection.
- Process engineering.
- Chemical handling.
- Specialist design such as laboratories.
- Security systems.
- Information and communications technology.
- Connections to statutory utilities.
- Planning applications (in particular outline planning applications).
- Furniture and equipment.
- Fixtures and fittings.
- Geotechnical surveys.
- Topographical and setting-out surveys.
- Demolition.
- Specification writing.
- External lighting.
- Alterations to existing buildings.
- Lifts and escalators.
- Models and mock-ups.
- BIM services.
- Building control submissions.
- Supervision and inspection during construction.
- Record drawings.
- Provision of certificates.
- Insurance claims.
Tasks that might be considered 'additional services' not covered by a consultant's standard fee unless specifically agreed might include:
- Acting as lead designer, contract administrator or lead consultant.
- Detailed thermal modelling.
- Environmental assessments.
- Options appraisal.
- Preparing or compiling the brief.
- Post-occupancy evaluations.
- Outline planning applications.
- Planning appeals.
- Assistance applying for grants or other funding.
- Post-occupancy advice on letting, rating, maintenance, energy consumption, insurance, tenant queries and facilities management.
- Assisting in the preparation of tender documents for maintenance and operation contracts.
- Preparing a building user's guide (a non-technical guide with information for users about environmental controls, access, security and safety systems etc).
- Provision of unusual visual representations or models.
- Building information modelling (BIM).
- Preparation of marketing materials.
- Preparation of as-built information.
- Party wall services.
- Site surveys.
- Whole-life costing studies.
- Environmental and ecological studies.
- Site selection.
- Provision of site inspectors.
- Assessment of alternative designs submitted by others (for example during the tender process for the main contractor).
- Dealing with claims and disputes.
- Services in relation to legal agreements.
- As-built drawings (many key systems will be shown 'as manufactured and installed' on specialist drawings and so general arrangement drawings may only be relevant as location drawings or for indicating zoning issues such as compartmentation).
Once the scope of services has been agreed by the parties, and either included in, or appended to the appointment agreement, or referred to in it, then any subsequent changes will need the consent of both parties.
NB The RIBA Plan of Work 2013 defines a schedule of services as: 'A list of specific services and tasks to be undertaken by a party involved in the project which is incorporated into their professional services contract.'
[edit] Related articles on Designing Buildings Wiki
- Appointing consultants.
- Architects fees.
- Collaborative practices.
- Consultant team.
- Consultant's proposals.
- Design liability.
- Designers.
- Employer's information requirements.
- Fees.
- Fee proposals.
- Framework agreements.
- Integrated Supply Team.
- Letter of appointment.
- Pre-qualification questionnaire.
- Procurement route.
- Professional Indemnity Insurance clause in conditions of engagement.
- Professional indemnity insurance.
- Request for proposals.
- Schedule.
- Scope creep.
- Scope of work.
- Structural engineer fees.
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.