Planning appeal
If planning permission is refused, the applicant may lodge an appeal which will then usually be decided by an inspector acting for the Secretary of State. A small number may be 'recovered' by the Secretary of State who will then determine the appeal themselves. See Recovered planning appeals for more information.
There are different types of appeal that can be made:
- Householder appeal.
- Planning appeal.
- Enforcement appeal.
- Listed building / conservation area appeal.
- Listed building / conservation area enforcement appeal.
- Lawful development certificate appeal.
- Advertisement appeal.
Time limits for appeals vary depending on the nature of the application, but for a standard planning application for a commercial development, appeals must be made within 6 months of the date of the decision notice.
Detailed procedures for making an appeal vary depending on the nature of the application, but generally the two parties to the appeal (usually the applicant and the local planning authority) will be expected to provide information to support their cases. The inspector will tell the parties what the timetable is for this information to be provided. The inspector will usually visit the site, and may hold a hearing. Some appeals, in particular those dealing with bigger developments, may be heard by public inquiry.
There is generally no fee for making an appeal (apart from enforcement appeals). Parties to appeals are normally expected to meet their own expenses, however where one party has behaved ‘unreasonably’ and has caused another party to incur unnecessary expense, an application for costs can be made and the Secretary of State or the inspector may make an award of costs. Awards of costs must be ‘reasonable’ and may be awarded both on application and at the initiative of the inspector.
A draft statement of common ground (SoCG) is a written statement containing factual information about the proposal which is the subject of the appeal that the appellant reasonably considers will not be disputed by the local planning authority. SoCG can be extremely valuable to inspectors and can improve the effectiveness and efficiency of the process. The guidance is intended to assist all professional representatives and expert witnesses in compliance with their duty to assist the inspector. For more information see: Statement of common ground
The delay to a project associated with making an appeal may have significant implications. The time from submitting an appeal to getting a decision may be several months.
Planning appeals may require additional services from the consultant team not covered by their initial appointment.
[edit] 2013 Reform
In October 2013, changes were introduced intended to speed up the appeals process, with an expectation that 80% of written representation appeals should be decided within 14 weeks and 80% of non-bespoke inquiries within 22 weeks:
At the point of launching their appeal, developers must present a full statement of their case (a written statement setting out full particulars of the case and copies of any documents that will be referred to or put in evidence), an explanation of the choice of procedure, and if there is likely to be a hearing or inquiry, a draft statement of common ground (a written statement setting out information about the proposal that it is not expected will be disputed by the local planning authority). The appeal will not be validated unless the developer complies with this requirement.
The planning authority must respond within one week with a questionnaire, reach an agreement on any statement of common ground within five weeks, and submit its final comments within seven weeks.
Complaints against appeals decisions are dealt with by the Planning Inspectorate’s Quality Assurance Unit. It is only possible to challenge appeals decisions in the High Court by showing that the Planning Inspectorate has misinterpreted the law. The Planning Inspectorate will then look at the decision again, but it will not necessarily be reversed. Applications to challenge decisions must be received by the Administrative Court within 42 days from the date of the decision.
[edit] Ongoing review
In July 2014, the government announced that it would give particular scrutiny to planning appeals in, or close to, neighbourhood plan areas, considering recovery of appeals for '...proposals for residential development of over 10 units in areas where a qualifying body has submitted a neighbourhood plan proposal to the local planning authority: or where a neighbourhood plan has been made'. (Ref. Written ministerial statement, 10 July 2014.)
In June 2018, Communities Secretary Rt. Hon James Brokenshire MP appointed Bridget Rosewell to chair an independent review into planning appeal inquiries. The review was set up with the aim of reducing the time it takes to determine inquiries established to resolve disputed planning proposals, whilst still ensuring quality decision making.
In February 2019, the government publish the findings of the independent review into planning appeal inquiries (the Rosewell Report) which proposed driving down the time taken to decide appeals from 47 to 26 weeks. Ref https://www.gov.uk/government/news/appeal-decisions-could-be-cut-by-5-months
In March 2019 it was announced that the Planning Inspectorate would run a pilot scheme for inquiries in response to the recommendations of the inquiries review. Ref https://www.gov.uk/government/news/inquiries-review
On 14 May 2019, the Planning Inspectorate published its action plan to implement the recommendations of the inquiries review. Ref https://www.gov.uk/government/news/inquiries-review-action-plan
For more information see: Rosewell Review.
[edit] Related articles on Designing Buildings
- Detailed planning permission.
- Enforcement notice.
- Judicial review.
- Outline planning permission.
- National Planning Policy Framework.
- Planning court.
- Planning enforcement.
- Planning fees.
- Planning inspectorate.
- Planning objection.
- Planning obligations.
- Planning permission.
- Recovered planning appeal.
- Planning related applications for judicial review.
- Rosewell Review.
- Statement of common ground.
- Statutory approvals.
- Statutory authorities.
- Stop notice.
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.