Schedule of rates for construction
Contents |
[edit] Introduction
In its most simple form, a schedule of rates can be a list in a contract setting out the staff, labour and plant hire rates the contractor will use for pricing cost reimbursable instructed daywork.
However, on a much larger scale, a 'schedule of rates term contract', 'term contract' or 'measured term contract' may be used when the nature of work required is known but it cannot be quantified, or if continuity of programme cannot be determined. In the absence of an estimate, tenderers quote unit rates against a document that is intended to cover all likely activities that might form part of the works.
As the extent of the work is unknown, the unit rates include overheads and profit. General preliminaries such as scaffolding, temporary power, supervision and temporary accommodation will also have rates. On projects longer than around 18 months there might be escalation provisions based on annual percentage increases.
[edit] Pros and cons
The advantages of schedule of rates term contracts include:
- Variations are easier to estimate and normally cheaper than on fixed price traditional contracts.
- The client can stop and start work at a pace that might be determined by cash flow or funding.
- A larger pool of contractors can be asked to tender as the process is inexpensive and quick.
- It is flexible in relation to scope and contractual commitment.
- As a fully-detailed design is not required the client can obtain tenders at the early stages of a project and begin construction before completion of the design. So to this extent it is 'fast track'.
The disadvantages include:
- Additional resources are required to measure work and certify payments.
- The client does not have a final price when committing to starting work.
- It is difficult for contractors to plan long-term resources and so might mean changes to personnel with loss of continuity.
- Contractors may be tempted to front-load costs in case later work does not materialise.
- There is no real incentive for contractors to treat such work with any sense of urgency and its best staff will be placed on the projects where the contractor is carrying more risk.
The tender documents will be a substantial package looking like a bill of quantities with numerous options and discount opportunities based on quantity.
[edit] Tender documents
Tender documents might have the following headings:
[edit] General conditions
- Methods of measurement.
- Qualification of star and proportional rates.
- Site preliminaries.
- Treatment of overtime rates.
- Codes of practice.
- Inclusion of protection, waste, transportation and health and safety compliance.
- Approved list of suppliers.
- What is included in rates,such as all subsistence and travel expenses.
- Client direct supplies and directly employed tradesmen.
- Testing and commissioning.
- Curved work premium.
- Definitions as used in the document.
[edit] Building work
- Demolition.
- Geotechnical investigation.
- Excavation.
- Concrete work.
- Brick and blockwork and masonry.
- Roofing and tanking.
- Scaffolding and staging.
- Carpentry and joinery.
- Ironmongery.
- Steel and metalwork.
- Fire shutters.
- Plasterwork, floor, wall, ceiling finishes.
- Plumbing and drainage including cable ducts.
- Fixtures, fittings and soft furnishings.
- Demountable partitions, dry walling and cubicles.
- External works.
- Labour.
- Plant and equipment hire.
[edit] Mechanical and electrical, lifts and escalators
- Electrical installation.
- High voltage switchgear.
- Transformers.
- Low voltage switchgear.
- Standby generators.
- Air conditioning and ventilation.
- Building Management System (BMS) controls.
- Fire services.
- Town gas.
- Catering equipment.
- Intruder alarm.
- Public address system.
- External lighting and electric gates.
- Lifts.
- Escalators.
- Cleaning cradle system.
Each of these headings will cover numerous elements which then have to be broken down into pricing units. For instance brick, blockwork and masonry might include a section called natural marble or granite slabs/tiles of any shape, size pattern or colour :
[edit] Benchmark rates
A number of indices are available providing benchmark rates that can be used for estimating purposes, such as the BCIS Schedule of Rates, the PSA Schedule of Rates, and so on.
[edit] Related articles on Designing Buildings
- Admeasurement.
- Bill of quantities.
- Charge-out rate.
- Construction contract.
- Construction person year.
- Difference between lump sum and measurement contracts.
- Henry Boot Construction Ltd v Alstom Combined Cycles.
- Measurement contract.
- Preliminaries.
- Procurement route.
- Rates.
- Remeasurement.
- Schedule.
- Tender documents.
- Term contract.
- Unit rates basis of payment.
Featured articles and news
Classroom electrician courses a 'waste of money'
Say experts from the Electrical Contractors’ Association.
Wellbeing in Buildings TG 10/2025
BSRIA topic guide updates.
With brief background and WELL v2™.
From studies, to books to a new project, with founder Emma Walshaw.
Types of drawings for building design
Still one of the most popular articles the A-Z of drawings.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
The remarkable story of a Highland architect.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
Comments
Here is an example of a schedule of rates for UK building, construction and maintenance works:
(http://www.constructionrates.co.uk/Schedule_of_Rates/Construction_National_Schedule_Rates_Measurement_NRSM_Dynamic.html)
and another example of a Schedule Of Rates (SOR) for Singapore Housing and Development Board (HDB) building tradesmen & repair works:
(https://hdb-sor.netlify.app)