Project monitoring
Contents |
[edit] Introduction
Project monitoring is the process or protecting the client’s interests from the risks associated with their interest in a development that is not under their direct control.
A project monitor is appointed, not to assume the responsibilities of the project manager or developer, but to act as an investigator and advisor to the client, responsible for protecting their interests in the development as it proceeds. In effect, the project monitor acts as the ‘eyes and ears’ of the client during the development process.
Project monitoring services can be carried out for a range of different client types:
- A funding institution which will acquire the project as an investment upon completion.
- A tenant or purchaser who will commit to lease or purchase the project upon completion.
- A bank or development finance company.
- Grant funders.
- Private finance initiative (PFI) funders.
The project monitor assesses the project as it progresses in a way that is both independent and impartial. They generally adopt a proactive rather than reactive approach, providing a form of ‘early warning system’ for the client, anticipating potential issues which may affect the project delivery. In this way, the project monitor can also be of value to the developer, as they can help ensure there is better-informed decision-making.
Issues that the project monitor will typically advise on include:
- Land and property acquisition.
- Statutory consents.
- Issues relating to the developer and project management systems.
- Financial appraisals.
- Construction agreements
- Costs.
- Programme.
- Design and construction quality.
Some of the advantages to the client of hiring a project monitor include:
- Enhanced risk management.
- Enhanced financial management.
- Enhanced programme management.
- Enhanced quality management.
- Greater protection of the client’s interests.
- Better-informed decision making.
[edit] Appointing a project monitor
Project monitors typically come from a background of surveying, commercial or project management. The specific competencies required depend on the nature fo the project. Specific sector knowledge can be an important quality for project monitors.
Upon receiving an initial inquiry, the project monitor should ensure they have the capability to provide the service required and advise the client accordingly if they are not fully competent in terms of the requirements of the project. Under certain circumstances, they may appoint a specialist sub-consultant to help them.
Before reaching a formal agreement on their appointment, the project monitor should have:
- An understanding of the project brief.
- A copy of the terms and conditions of any funding, purchase, tenancy, loan or other third party agreements.
- A scope of services required.
- Contractual terms of the appointment.
- The correct level of professional indemnity insurance.
It is generally advisable that project monitors are appointed based on the potential added value they can bring to the development, rather than solely on the lowest fee level.
[edit] Duties of the project monitor
The project monitor is reliant on the development team for the acquisition of the necessary information to perform their role. It is important, therefore, that the development team understand the need to cooperate and make information available, and measures should be put in place in the agreements between client and developer to ensure this is the case.
There are a number of key reports that a project monitor may produce during the course of a project.
[edit] Initial audit report
This report allows the project monitor to develop a close understanding of the project. It should fully cover the following:
- The specification.
- Design brief and constraints.
- Development appraisal.
- Cost plan.
- Design and construction programme.
- Design and construction team.
- Risks associated with the project.
[edit] Progress reports
Progress reports often coincide with key milestones, such; completion of design stages, the start of construction or the procurement of a construction contract. Progress reports will usually continue up to the completion of the development or the client’s interest in the development.
It is important that such reports are produced in time to inform any client decisions that are required, rather than simply acting as a record of what has happened.
[edit] Practical completion
The project monitor should prepare a completion report at this stage. This typically includes:
- Relevant statutory and non-statutory consents.
- Any defects schedules or lists of outstanding works.
- Financial report.
- Lessons learned.
- Recommendations.
- Handover documentation such as; health and safety file, relevant certificates,draft building owner's manual, building log book, building user's guide, testing and commissioning data and so on. For more information see: Handover construction site to the client.
[edit] Related articles on Designing Buildings Wiki
- Appointing consultants.
- Client.
- Client BIM adviser.
- Client design adviser.
- Conceiving construction plans.
- Construction project manager - morning tasks.
- Contract administrator.
- Employer's agent.
- Handover construction site to the client.
- Independent client advisers.
- Lead consultant for building design.
- Microsoft's six ways to supercharge project management
- Monte Carlo simulation.
- Project manager.
[edit] External resources
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.